Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
42
matching recommendationsSIC | 38 | Instruments And Related Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0356 # 04 Y:1988 | 04 | 1988 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,430 | $1,000 | Implemented |
MA0131 # 01 Y:1988 | 01 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $749 | $1,042 | Implemented |
GT0356 # 06 Y:1988 | 06 | 1988 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $27,600 | $10,000 | Not Implemented |
GT0356 # 05 Y:1988 | 05 | 1988 | IMPROVE LUBRICATION PRACTICES | $10,600 | $1,830 | Implemented |
MA0131 # 04 Y:1988 | 04 | 1988 | INSTALL / REPAIR INSULATION ON STEAM LINES | $449 | $324 | Implemented |
GT0356 # 03 Y:1988 | 03 | 1988 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,859 | $8,805 | Implemented |
GT0356 # 02 Y:1988 | 02 | 1988 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,342 | $3,313 | Not Implemented |
GT0356 # 01 Y:1988 | 01 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,680 | $32,200 | Implemented |
MA0131 # 02 Y:1988 | 02 | 1988 | DE-ENERGIZE EXCESS TRANSFORMER CAPACITY | $604 | $1,292 | Not Implemented |
MA0131 # 03 Y:1988 | 03 | 1988 | INSULATE BARE EQUIPMENT | $435 | $161 | Implemented |
MA0131 # 05 Y:1988 | 05 | 1988 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $876 | $3,000 | Implemented |
LT0129 # 02 Y:1988 | 02 | 1988 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $500 | $0 | Not Implemented |
RU0033 # 01 Y:1988 | 01 | 1988 | IMPROVE LUBRICATION PRACTICES | $743 | $800 | Not Implemented |
LT0129 # 09 Y:1988 | 09 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $53 | $55 | Implemented |
LT0129 # 08 Y:1988 | 08 | 1988 | INSTALL TIMERS AND/OR THERMOSTATS | $590 | $600 | Not Implemented |
LT0129 # 07 Y:1988 | 07 | 1988 | AIR CONDITION ONLY SPACE NECESSARY | $6,100 | $6,000 | Not Implemented |
LT0129 # 06 Y:1988 | 06 | 1988 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,020 | $0 | Implemented |
LT0129 # 05 Y:1988 | 05 | 1988 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,520 | $5,557 | Implemented |
LT0129 # 04 Y:1988 | 04 | 1988 | USE RADIANT HEATER FOR SPOT HEATING | $9,900 | $5,000 | Not Implemented |
LT0129 # 03 Y:1988 | 03 | 1988 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,300 | $7,900 | Not Implemented |
RU0033 # 03 Y:1988 | 03 | 1988 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,608 | $302 | Implemented |
LT0129 # 01 Y:1988 | 01 | 1988 | INSULATE BARE EQUIPMENT | $6,480 | $5,500 | Implemented |
RU0033 # 05 Y:1988 | 05 | 1988 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $4,749 | $0 | Implemented |
RU0033 # 09 Y:1988 | 09 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,508 | $244 | Implemented |
RU0033 # 02 Y:1988 | 02 | 1988 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,044 | $0 | Not Implemented |