Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
276
matching recommendationsSIC | 382 | Measuring And Controlling Devices |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0136 # 02 Y:1996 | 02 | 1996 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $2,074 | $2,083 | Implemented |
SD0136 # 03 Y:1996 | 03 | 1996 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,321 | $40 | Implemented |
SD0136 # 04 Y:1996 | 04 | 1996 | USE OPTIMUM THICKNESS INSULATION | $1,905 | $651 | Implemented |
SD0136 # 05 Y:1996 | 05 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,979 | $5,928 | Implemented |
SD0136 # 06 Y:1996 | 06 | 1996 | INSTALL SPECTRAL REFLECTORS / DELAMP | $6,002 | $4,080 | Implemented |
SD0136 # 07 Y:1996 | 07 | 1996 | INSTALL OCCUPANCY SENSORS | $1,471 | $1,001 | Implemented |
SD0136 # 08 Y:1996 | 08 | 1996 | REDUCE SCRAP PRODUCTION | $56,160 | $0 | Implemented |
SF0080 # 01 Y:1996 | 01 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $22,008 | $70,980 | Not Implemented |
SF0080 # 02 Y:1996 | 02 | 1996 | INSTALL OCCUPANCY SENSORS | $4,085 | $11,200 | Not Implemented |
SF0080 # 03 Y:1996 | 03 | 1996 | INSTALL OCCUPANCY SENSORS | $8,168 | $1,680 | Not Implemented |
SF0080 # 04 Y:1996 | 04 | 1996 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $5,815 | $13,397 | Implemented |
SF0080 # 05 Y:1996 | 05 | 1996 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $67 | $100 | Implemented |
SF0080 # 06 Y:1996 | 06 | 1996 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,740 | $9,900 | Implemented |
SF0080 # 07 Y:1996 | 07 | 1996 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,096 | $3,194 | Not Implemented |
SF0080 # 08 Y:1996 | 08 | 1996 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $662 | $2,200 | Not Implemented |
SF0080 # 09 Y:1996 | 09 | 1996 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $2,218 | $6,800 | Not Implemented |
SF0080 # 10 Y:1996 | 10 | 1996 | CONVERT TO AQUEOUS CLEANING SYSTEM | $1,660 | $5,561 | Implemented |
NV0006 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,709 | $-175 | Implemented |
NV0006 # 02 Y:1994 | 02 | 1994 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $2,218 | $3,780 | Not Implemented |
NV0006 # 03 Y:1994 | 03 | 1994 | INSTALL OCCUPANCY SENSORS | $914 | $454 | Not Implemented |
NV0006 # 04 Y:1994 | 04 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $554 | $240 | Implemented |
NV0006 # 05 Y:1994 | 05 | 1994 | OPTIMIZE PLANT POWER FACTOR | $807 | $2,250 | Not Implemented |
NV0006 # 06 Y:1994 | 06 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $394 | $30 | Implemented |
SD0088 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,963 | $4,300 | Implemented |
SD0088 # 02 Y:1994 | 02 | 1994 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $6,722 | $200 | Implemented |