Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
36
matching recommendationsSIC | 382 | Measuring And Controlling Devices |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0100 # 13 Y:1987 | 13 | 1987 | AIR CONDITION ONLY SPACE NECESSARY | $3,390 | $5,100 | Implemented |
CO0100 # 12 Y:1987 | 12 | 1987 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $631 | $1,400 | Not Implemented |
CO0100 # 11 Y:1987 | 11 | 1987 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,700 | $400 | Implemented |
CO0100 # 10 Y:1987 | 10 | 1987 | INSTALL TIMERS AND/OR THERMOSTATS | $13,949 | $6,000 | Implemented |
CO0100 # 09 Y:1987 | 09 | 1987 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $1,768 | $5,000 | Not Implemented |
CO0100 # 08 Y:1987 | 08 | 1987 | ISOLATE HOT OR COLD EQUIPMENT | $9,865 | $6,000 | Implemented |
CO0100 # 07 Y:1987 | 07 | 1987 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $20,936 | $2,000 | Implemented |
CO0100 # 06 Y:1987 | 06 | 1987 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $1,877 | $125 | Implemented |
CO0100 # 05 Y:1987 | 05 | 1987 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $20,817 | $250 | Implemented |
CO0100 # 04 Y:1987 | 04 | 1987 | OPERATE BOILERS ON HIGH FIRE SETTING | $3,445 | $1,500 | Not Implemented |
CO0100 # 03 Y:1987 | 03 | 1987 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $50,411 | $138,000 | Implemented |
CO0100 # 01 Y:1987 | 01 | 1987 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,308 | $300 | Implemented |
CO0100 # 02 Y:1987 | 02 | 1987 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $242 | $450 | Not Implemented |
KU0230 # 02 Y:1987 | 02 | 1987 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $3,808 | $1,200 | Not Implemented |
KU0230 # 12 Y:1987 | 12 | 1987 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $121 | $520 | Implemented |
KU0230 # 11 Y:1987 | 11 | 1987 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $191 | $0 | Implemented |
KU0230 # 10 Y:1987 | 10 | 1987 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $290 | $500 | Not Implemented |
KU0230 # 09 Y:1987 | 09 | 1987 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $314 | $205 | Implemented |
KU0230 # 08 Y:1987 | 08 | 1987 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $437 | $0 | Implemented |
KU0230 # 07 Y:1987 | 07 | 1987 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $605 | $90 | Not Implemented |
KU0230 # 06 Y:1987 | 06 | 1987 | IMPROVE LUBRICATION PRACTICES | $677 | $400 | Not Implemented |
KU0230 # 05 Y:1987 | 05 | 1987 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,040 | $0 | Implemented |
KU0230 # 04 Y:1987 | 04 | 1987 | INSTALL AUTOMATIC STACK DAMPER | $1,486 | $2,600 | Implemented |
KU0230 # 03 Y:1987 | 03 | 1987 | HEAT WATER WITH EXHAUST HEAT | $3,795 | $7,000 | Not Implemented |
KU0230 # 01 Y:1987 | 01 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,144 | $615 | Implemented |