Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,840
matching recommendationsSIC | 384 | Medical Instruments And Supplies |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0583 # 02 Y:2022 | 02 | 2022 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $44,987 | $62,001 | Implemented |
UF0583 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,746 | $33,000 | Implemented |
UF0583 # 04 Y:2022 | 04 | 2022 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $13,240 | $0 | Implemented |
UF0583 # 05 Y:2022 | 05 | 2022 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $273,973 | $0 | Not Implemented |
UF0583 # 06 Y:2022 | 06 | 2022 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $58,774 | $10,000 | Not Implemented |
NL0069 # 01 Y:2022 | 01 | 2022 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $459,130 | $2,266,822 | Not Implemented |
NL0069 # 02 Y:2022 | 02 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $100,270 | $900 | Not Implemented |
NL0069 # 03 Y:2022 | 03 | 2022 | UPGRADE CONTROLS ON COMPRESSORS | $64,154 | $20,000 | Not Implemented |
NL0069 # 04 Y:2022 | 04 | 2022 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $11,908 | $110,400 | Not Implemented |
NL0069 # 05 Y:2022 | 05 | 2022 | RECOVER AND REUSE WASTE MATERIAL | $10,312 | $3,180 | Not Implemented |
NL0069 # 06 Y:2022 | 06 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,221 | $1,069 | Not Implemented |
NL0069 # 07 Y:2022 | 07 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $599 | $1,397 | Not Implemented |
MZ0329 # 01 Y:2022 | 01 | 2022 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $382 | $240 | Not Implemented |
MZ0329 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,529 | $20,439 | Implemented |
MZ0329 # 03 Y:2022 | 03 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $540 | $3,202 | Not Implemented |
MZ0329 # 04 Y:2022 | 04 | 2022 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $11,471 | $60,924 | Not Implemented |
MZ0329 # 05 Y:2022 | 05 | 2022 | INSULATE BARE EQUIPMENT | $583 | $960 | Implemented |
MZ0329 # 06 Y:2022 | 06 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $983 | $150 | Implemented |
MZ0329 # 07 Y:2022 | 07 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,853 | $4,331 | Not Implemented |
LE0528 # 01 Y:2022 | 01 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,359 | $40 | Not Implemented |
LE0528 # 02 Y:2022 | 02 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $2,953 | $1,000 | Implemented |
LE0528 # 03 Y:2022 | 03 | 2022 | UPGRADE OBSOLETE EQUIPMENT | $150,000 | $90,000 | Implemented |
LE0528 # 04 Y:2022 | 04 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,512 | $150 | Implemented |
LE0528 # 05 Y:2022 | 05 | 2022 | UPGRADE OBSOLETE EQUIPMENT | $150,000 | $150,000 | Implemented |
LE0528 # 06 Y:2022 | 06 | 2022 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,188 | $2,000 | Not Implemented |