Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
24
matching recommendationsSIC | 3841 | Surgical And Medical Instruments |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0325 # 08 Y:2003 | 08 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,279 | $1,410 | Not Implemented |
SD0325 # 07 Y:2003 | 07 | 2003 | INSTALL SKYLIGHTS | $9,297 | $18,000 | Not Implemented |
SD0325 # 06 Y:2003 | 06 | 2003 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $14,542 | $0 | Not Implemented |
SD0325 # 05 Y:2003 | 05 | 2003 | INSTALL TIMERS AND/OR THERMOSTATS | $36,071 | $1,000 | Implemented |
SD0325 # 04 Y:2003 | 04 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $37,849 | $2,000 | Implemented |
SD0325 # 03 Y:2003 | 03 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $53,956 | $32,725 | Implemented |
SD0325 # 02 Y:2003 | 02 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $71,754 | $0 | Implemented |
SD0325 # 01 Y:2003 | 01 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $88,041 | $300,075 | Not Implemented |
LE0156 # 04 Y:2003 | 04 | 2003 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,340 | $0 | Implemented |
LE0156 # 07 Y:2003 | 07 | 2003 | INSTALL OCCUPANCY SENSORS | $239 | $600 | Implemented |
LE0156 # 06 Y:2003 | 06 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $844 | $0 | Not Implemented |
LE0156 # 05 Y:2003 | 05 | 2003 | INSULATE BARE EQUIPMENT | $1,413 | $0 | Implemented |
LE0156 # 03 Y:2003 | 03 | 2003 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $5,466 | $0 | Not Implemented |
LE0156 # 02 Y:2003 | 02 | 2003 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $14,320 | $750 | Not Implemented |
LE0156 # 01 Y:2003 | 01 | 2003 | SIZE AIR HANDLING GRILLS/ DUCT/S COILS TO MINIMIZE AIR RESISTANCE | $1,112 | $870 | Implemented |
AM0437 # 01 Y:2003 | 01 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $10,100 | $0 | Implemented |
AM0437 # 09 Y:2003 | 09 | 2003 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $3,464 | $350 | Implemented |
AM0437 # 08 Y:2003 | 08 | 2003 | USE PHOTOCELL CONTROLS | $1,110 | $110 | Implemented |
AM0437 # 07 Y:2003 | 07 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $975 | $785 | Implemented |
AM0437 # 06 Y:2003 | 06 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,500 | $0 | Not Implemented |
AM0437 # 05 Y:2003 | 05 | 2003 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $2,110 | $0 | Implemented |
AM0437 # 04 Y:2003 | 04 | 2003 | INSULATE BARE EQUIPMENT | $4,480 | $1,380 | Implemented |
AM0437 # 03 Y:2003 | 03 | 2003 | USE SYNTHETIC LUBRICANT | $5,500 | $0 | Not Implemented |
AM0437 # 02 Y:2003 | 02 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,670 | $1,900 | Implemented |