Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
29
matching recommendationsSIC | 3851 | Ophthalmic Goods |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0153 # 03 Y:1985 | 03 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,131 | $5,120 | Implemented |
KU0153 # 17 Y:1985 | 17 | 1985 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $234 | $43 | Implemented |
KU0153 # 16 Y:1985 | 16 | 1985 | INSULATE BARE EQUIPMENT | $244 | $35 | Not Implemented |
KU0153 # 15 Y:1985 | 15 | 1985 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $105 | $50 | Implemented |
KU0153 # 14 Y:1985 | 14 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $294 | $43 | Implemented |
KU0153 # 13 Y:1985 | 13 | 1985 | RECOVER WASTE HEAT FROM EQUIPMENT | $586 | $175 | Implemented |
KU0153 # 12 Y:1985 | 12 | 1985 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $461 | $100 | Not Implemented |
KU0153 # 11 Y:1985 | 11 | 1985 | INSTALL AUTOMATIC STACK DAMPER | $636 | $1,000 | Not Implemented |
KU0153 # 10 Y:1985 | 10 | 1985 | AIR CONDITION ONLY SPACE NECESSARY | $517 | $1,060 | Implemented |
KU0153 # 09 Y:1985 | 09 | 1985 | USE MINIMUM SAFE OVEN VENTILATION | $1,573 | $2,800 | Implemented |
KU0153 # 08 Y:1985 | 08 | 1985 | COVER OPEN TANKS | $3,927 | $600 | Implemented |
KU0153 # 07 Y:1985 | 07 | 1985 | IMPROVE LUBRICATION PRACTICES | $610 | $0 | Implemented |
KU0153 # 06 Y:1985 | 06 | 1985 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,250 | $2,500 | Implemented |
KU0153 # 05 Y:1985 | 05 | 1985 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $1,363 | $200 | Implemented |
KU0153 # 04 Y:1985 | 04 | 1985 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,055 | $0 | Implemented |
KU0153 # 02 Y:1985 | 02 | 1985 | INSULATE BARE EQUIPMENT | $5,507 | $1,300 | Implemented |
KU0153 # 01 Y:1985 | 01 | 1985 | INSTALL TIMERS AND/OR THERMOSTATS | $10,215 | $10,000 | Implemented |
KU0151 # 01 Y:1985 | 01 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,200 | $890 | Implemented |
KU0151 # 12 Y:1985 | 12 | 1985 | COVER OPEN TANKS | $143 | $280 | Not Implemented |
KU0151 # 11 Y:1985 | 11 | 1985 | INSULATE BARE EQUIPMENT | $197 | $56 | Not Implemented |
KU0151 # 10 Y:1985 | 10 | 1985 | INSULATE BARE EQUIPMENT | $214 | $66 | Not Implemented |
KU0151 # 09 Y:1985 | 09 | 1985 | INSULATE BARE EQUIPMENT | $272 | $290 | Not Implemented |
KU0151 # 08 Y:1985 | 08 | 1985 | INSULATE BARE EQUIPMENT | $143 | $144 | Not Implemented |
KU0151 # 07 Y:1985 | 07 | 1985 | INSULATE BARE EQUIPMENT | $378 | $240 | Not Implemented |
KU0151 # 06 Y:1985 | 06 | 1985 | IMPROVE LUBRICATION PRACTICES | $316 | $94 | Implemented |