IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

37

matching recommendations
Reset
SIC 39 Miscellaneous Manufacturing Industries
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CO0646 # 02 Y:2011 02 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,270 $7,320 Not Implemented
CO0646 # 03 Y:2011 03 2011 USE DOUBLE OR TRIPLE GLAZED WINDOWS TO MAINTAIN HIGHER RELATIVE HUMIDITY AND TO REDUCE HEAT LOSSES $2,120 $10,000 Implemented
CO0646 # 04 Y:2011 04 2011 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $2,080 $14,690 Not Implemented
CO0646 # 05 Y:2011 05 2011 USE SOLAR HEAT TO MAKE ELECTRICTY $1,910 $35,000 Not Implemented
CO0646 # 06 Y:2011 06 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,340 $2,730 Implemented
CO0646 # 07 Y:2011 07 2011 INSTALL WIND POWERED ELECTRIC GENERATOR $270 $5,260 Not Implemented
CO0646 # 08 Y:2011 08 2011 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $150 $40 Implemented
CO0646 # 01 Y:2011 01 2011 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $8,270 $62,380 Not Implemented
MI0201 # 06 Y:2011 06 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,700 $1,210 Not Implemented
MI0201 # 04 Y:2011 04 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $16,184 $41,193 Not Implemented
MI0201 # 02 Y:2011 02 2011 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $27,894 $2,000 Implemented
MI0201 # 03 Y:2011 03 2011 TURN OFF EQUIPMENT WHEN NOT IN USE $18,870 $7,920 Implemented
MI0201 # 08 Y:2011 08 2011 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $4,894 $2,200 Implemented
MI0201 # 07 Y:2011 07 2011 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,900 $40 Implemented
MI0201 # 01 Y:2011 01 2011 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD $36,428 $124,975 Not Implemented
MI0201 # 05 Y:2011 05 2011 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $6,322 $1,275 Not Implemented
UF0441 # 09 Y:2011 09 2011 UTILIZE SENSORS CONTROLLING ROOF AND WALL OPENINGS $11,651 $9,970 Not Implemented
UF0441 # 08 Y:2011 08 2011 INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE $23,120 $7,950 Not Implemented
UF0441 # 07 Y:2011 07 2011 INSTALL TIMERS AND/OR THERMOSTATS $713 $90 Not Implemented
UF0441 # 01 Y:2011 01 2011 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $1,243 $0 Not Implemented
UF0441 # 02 Y:2011 02 2011 LOWER LIGHT FIXTURES IN HIGH CEILING AREAS $8,379 $5,375 Not Implemented
UF0441 # 03 Y:2011 03 2011 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $3,216 $225 Not Implemented
UF0441 # 04 Y:2011 04 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,987 $4,040 Not Implemented
UF0441 # 05 Y:2011 05 2011 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $10,497 $4,335 Not Implemented
UF0441 # 06 Y:2011 06 2011 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $426 $396 Not Implemented