Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,432
matching recommendationsSIC | 399 | Miscellaneous Manufactures |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
HO0108 # 02 Y:1995 | 02 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $311 | $436 | Implemented |
UL0126 # 01 Y:1995 | 01 | 1995 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $34,745 | $2,000 | Implemented |
UL0126 # 02 Y:1995 | 02 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,272 | $40 | Not Implemented |
UL0126 # 03 Y:1995 | 03 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,595 | $40 | Implemented |
UL0126 # 04 Y:1995 | 04 | 1995 | OPTIMIZE PLANT POWER FACTOR | $24,600 | $16,488 | Not Implemented |
UD0452 # 01 Y:1995 | 01 | 1995 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $620 | $0 | Not Implemented |
UD0452 # 02 Y:1995 | 02 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $8,950 | $0 | Implemented |
UD0452 # 03 Y:1995 | 03 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,856 | $4,320 | Not Implemented |
UD0452 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $680 | $880 | Not Implemented |
WI0226 # 01 Y:1995 | 01 | 1995 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $14,957 | $500 | Not Implemented |
WI0226 # 02 Y:1995 | 02 | 1995 | OPTIMIZE PLANT POWER FACTOR | $3,891 | $11,655 | Not Implemented |
WI0226 # 03 Y:1995 | 03 | 1995 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $6,018 | $500 | Implemented |
WI0226 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,930 | $7,100 | Implemented |
WI0226 # 05 Y:1995 | 05 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,502 | $0 | Implemented |
WI0226 # 06 Y:1995 | 06 | 1995 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $4,226 | $0 | Not Implemented |
WI0226 # 07 Y:1995 | 07 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $897 | $0 | Implemented |
WI0226 # 08 Y:1995 | 08 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $583 | $960 | Implemented |
WI0226 # 09 Y:1995 | 09 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $528 | $0 | Implemented |
WI0226 # 10 Y:1995 | 10 | 1995 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $23,500 | $0 | Not Implemented |
WI0218 # 01 Y:1994 | 01 | 1994 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $4,760 | $8,532 | Implemented |
WI0218 # 02 Y:1994 | 02 | 1994 | SCHEDULE ROUTINE MAINTENANCE DURING NON-OPERATING PERIODS | $7,498 | $0 | Implemented |
WI0218 # 03 Y:1994 | 03 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,927 | $4,569 | Not Implemented |
WI0218 # 04 Y:1994 | 04 | 1994 | INSTALL OCCUPANCY SENSORS | $518 | $300 | Not Implemented |
WI0218 # 05 Y:1994 | 05 | 1994 | REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY | $1,260 | $1,000 | Not Implemented |
WI0218 # 06 Y:1994 | 06 | 1994 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,148 | $500 | Implemented |