IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

12

matching recommendations
Reset
SIC 5153 Grain And Field Beans
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
NL0009 # 01 Y:2017 01 2017 REDESIGN PROCESS $37,689 $38,000 Not Implemented
NL0009 # 02 Y:2017 02 2017 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $10,263 $10,000 Not Implemented
NL0009 # 03 Y:2017 03 2017 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,632 $4,788 Implemented
NL0009 # 04 Y:2017 04 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $691 $3,360 Implemented
OK0936 # 01 Y:2016 01 2016 OPTIMIZE PLANT POWER FACTOR $46,436 $29,439 Implemented
OK0936 # 02 Y:2016 02 2016 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $27,106 $35,525 Not Implemented
OK0936 # 03 Y:2016 03 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $323 $450 Implemented
OK0936 # 04 Y:2016 04 2016 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $144 $316 Not Implemented
UK1215 # 01 Y:2013 01 2013 INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN $4,249 $2,200 Not Implemented
UK1215 # 02 Y:2013 02 2013 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,824 $4,516 Implemented
UK1215 # 03 Y:2013 03 2013 ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE $4,021 $1,610 Implemented
UK1215 # 04 Y:2013 04 2013 PAY UTILITY BILLS ON TIME $1,678 $0 Implemented