IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

142,775

matching recommendations
Reset
ARC 2 ENERGY MANAGEMENT
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UA0239 # 03 Y:2021 03 2021 OPTIMIZE PLANT POWER FACTOR $12,847 $4,947 Not Implemented
UA0239 # 04 Y:2021 04 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $9,348 $23,987 Implemented
UA0239 # 05 Y:2021 05 2021 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $364 $51 Implemented
UA0239 # 06 Y:2021 06 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,641 $9,144 Not Implemented
UA0239 # 07 Y:2021 07 2021 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $18,822 $2,500 Not Implemented
UA0239 # 08 Y:2021 08 2021 USE RADIANT HEATER FOR SPOT HEATING $794 $709 Not Implemented
LE0504 # 01 Y:2021 01 2021 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $205 $500 Implemented
LE0504 # 02 Y:2021 02 2021 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $1,280 $4,000 Not Implemented
LE0504 # 03 Y:2021 03 2021 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $3,847 $12,000 Implemented
LE0504 # 04 Y:2021 04 2021 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $2,323 $12,000 Implemented
LE0504 # 05 Y:2021 05 2021 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $61,283 $360,000 Implemented
CL2104 # 01 Y:2021 01 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,291 $14,832 Not Implemented
CL2104 # 02 Y:2021 02 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,151 $5,640 Not Implemented
CL2104 # 03 Y:2021 03 2021 INSULATE BARE EQUIPMENT $270 $250 Not Implemented
CL2104 # 04 Y:2021 04 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,440 $15,000 Not Implemented
CL2104 # 05 Y:2021 05 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $22,742 $2,100 Implemented
NC0660 # 01 Y:2021 01 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,499 $3,730 n/a
NC0660 # 02 Y:2021 02 2021 INSTALL COMMON HEADER ON COMPRESSORS $4,229 $10,000 n/a
NC0660 # 03 Y:2021 03 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $339 $100 n/a
NC0660 # 04 Y:2021 04 2021 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $3,563 $500 n/a
LE0503 # 01 Y:2021 01 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $21,633 $50,000 Implemented
LE0503 # 02 Y:2021 02 2021 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $11,108 $45,000 Implemented
LE0503 # 03 Y:2021 03 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,254 $17,500 Implemented
LE0503 # 04 Y:2021 04 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,126 $15,100 Implemented
LE0503 # 05 Y:2021 05 2021 PREHEAT COMBUSTION AIR WITH WASTE HEAT $56,981 $300,000 Implemented