Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
143,608
matching recommendationsARC | 2 | ENERGY MANAGEMENT |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0266 # 04 Y:1988 | 04 | 1988 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,624 | $100 | Implemented |
KU0266 # 06 Y:1988 | 06 | 1988 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $1,336 | $1,300 | Not Implemented |
KU0266 # 07 Y:1988 | 07 | 1988 | RECOVER WASTE HEAT FROM EQUIPMENT | $898 | $1,500 | Implemented |
KU0266 # 08 Y:1988 | 08 | 1988 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $406 | $580 | Not Implemented |
KU0254 # 01 Y:1988 | 01 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,185 | $2,000 | Implemented |
KU0254 # 02 Y:1988 | 02 | 1988 | INSTALL TIMERS AND/OR THERMOSTATS | $191 | $0 | Not Implemented |
KU0254 # 03 Y:1988 | 03 | 1988 | USE ONLY AMOUNT OF AIR NECESSARY TO PREVENT EXPLOSION HAZARD | $1,539 | $0 | Implemented |
KU0254 # 04 Y:1988 | 04 | 1988 | REPLACE BROKEN WINDOWS AND/OR WINDOW SASH | $1,773 | $1,800 | Not Implemented |
KU0254 # 05 Y:1988 | 05 | 1988 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $347 | $0 | Implemented |
KU0254 # 06 Y:1988 | 06 | 1988 | INSTALL AUTOMATIC STACK DAMPER | $2,033 | $2,125 | Not Implemented |
KU0254 # 07 Y:1988 | 07 | 1988 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,741 | $1,680 | Implemented |
KU0254 # 08 Y:1988 | 08 | 1988 | IMPROVE LUBRICATION PRACTICES | $159 | $0 | Implemented |
TN0353 # 01 Y:1988 | 01 | 1988 | KEEP LAMPS AND REFLECTORS CLEAN | $10,650 | $47,250 | Not Implemented |
TN0353 # 02 Y:1988 | 02 | 1988 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $5,083 | $19,050 | Not Implemented |
TN0353 # 03 Y:1988 | 03 | 1988 | INSULATE BARE EQUIPMENT | $1,253 | $2,380 | Implemented |
TN0353 # 04 Y:1988 | 04 | 1988 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,936 | $780 | Implemented |
TN0353 # 05 Y:1988 | 05 | 1988 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,251 | $0 | Implemented |
TN0353 # 06 Y:1988 | 06 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $488 | $689 | Implemented |
UD0271 # 01 Y:1989 | 01 | 1989 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,000 | $0 | Implemented |
UD0271 # 02 Y:1989 | 02 | 1989 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,360 | $0 | Implemented |
UD0271 # 03 Y:1989 | 03 | 1989 | REDESIGN PROCESS | $62,230 | $10,000 | Implemented |
UD0271 # 04 Y:1989 | 04 | 1989 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,591 | $500 | Implemented |
UD0271 # 05 Y:1989 | 05 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,761 | $27,100 | Implemented |
UD0272 # 01 Y:1989 | 01 | 1989 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $10,742 | $75,000 | Not Implemented |
UD0272 # 02 Y:1989 | 02 | 1989 | INSTALL SET-BACK TIMERS | $2,010 | $0 | Implemented |