IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

19

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
DL0191 # 03 Y:2021 03 2021 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $3,622 $600 Not Implemented
DL0191 # 12 Y:2021 12 2021 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $5,502 $22,000 Not Implemented
DL0191 # 11 Y:2021 11 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,536 $925 Not Implemented
DL0191 # 10 Y:2021 10 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,846 $1,500 Not Implemented
DL0191 # 09 Y:2021 09 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,391 $1,527 Not Implemented
DL0191 # 08 Y:2021 08 2021 INSTALL TIMERS AND/OR THERMOSTATS $687 $333 Not Implemented
DL0191 # 07 Y:2021 07 2021 RECOVER WASTE HEAT FROM EQUIPMENT $1,032 $4,500 Not Implemented
DL0191 # 06 Y:2021 06 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,208 $38 Not Implemented
DL0191 # 05 Y:2021 05 2021 USE REVERSE OSMOSIS TO CONCENTRATE MATERIAL $5,413 $1,000 Not Implemented
DL0191 # 04 Y:2021 04 2021 INSTALL / REPAIR INSULATION ON STEAM LINES $818 $168 Not Implemented
DL0191 # 02 Y:2021 02 2021 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $3,827 $0 Not Implemented
DL0191 # 01 Y:2021 01 2021 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $2,696 $0 Not Implemented
DL0189 # 01 Y:2021 01 2021 ELIMINATE LEAKS IN WATER LINES AND VALVES $5,300 $425 Implemented
DL0189 # 07 Y:2021 07 2021 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES $24,980 $15,000 Not Implemented
DL0189 # 06 Y:2021 06 2021 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $12,820 $24,000 Implemented
DL0189 # 05 Y:2021 05 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,110 $72,258 Implemented
DL0189 # 04 Y:2021 04 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $28,940 $20,000 Implemented
DL0189 # 03 Y:2021 03 2021 RECOVER WASTE HEAT FROM EQUIPMENT $6,300 $3,250 Not Implemented
DL0189 # 02 Y:2021 02 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $12,750 $2,550 Not Implemented