Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
254
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LL0294 # 08 Y:2008 | 08 | 2008 | INSTALL OCCUPANCY SENSORS | $645 | $90 | Implemented |
LL0294 # 07 Y:2008 | 07 | 2008 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,841 | $210 | Not Implemented |
LL0294 # 06 Y:2008 | 06 | 2008 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,006 | $1,880 | Not Implemented |
LL0294 # 05 Y:2008 | 05 | 2008 | INSULATE BARE EQUIPMENT | $4,740 | $2,539 | Not Implemented |
LL0294 # 04 Y:2008 | 04 | 2008 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $7,897 | $1,210 | Implemented |
LL0294 # 03 Y:2008 | 03 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,541 | $10,640 | Not Implemented |
LL0294 # 02 Y:2008 | 02 | 2008 | OPTIMIZE PLANT POWER FACTOR | $16,326 | $5,201 | Not Implemented |
LL0294 # 01 Y:2008 | 01 | 2008 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $31,560 | $45,800 | Not Implemented |
LL0289 # 08 Y:2008 | 08 | 2008 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $572 | $1,402 | Not Implemented |
LL0289 # 01 Y:2008 | 01 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $274,767 | $187,520 | Implemented |
LL0289 # 02 Y:2008 | 02 | 2008 | REPAIR AND ELIMINATE STEAM LEAKS | $110,300 | $3,650 | Implemented |
LL0289 # 03 Y:2008 | 03 | 2008 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $47,583 | $1,290 | Not Implemented |
LL0289 # 04 Y:2008 | 04 | 2008 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $21,390 | $11,905 | Not Implemented |
LL0289 # 05 Y:2008 | 05 | 2008 | INSULATE BARE EQUIPMENT | $7,830 | $1,940 | Not Implemented |
LL0289 # 09 Y:2008 | 09 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $333 | $165 | Implemented |
LL0289 # 07 Y:2008 | 07 | 2008 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,820 | $1,710 | Not Implemented |
LL0289 # 06 Y:2008 | 06 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,497 | $3,500 | Not Implemented |
LL0284 # 08 Y:2007 | 08 | 2007 | INSULATE BARE EQUIPMENT | $155 | $102 | Not Implemented |
LL0284 # 04 Y:2007 | 04 | 2007 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $16,900 | $1,500 | Not Implemented |
LL0284 # 03 Y:2007 | 03 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $21,045 | $12,575 | Not Implemented |
LL0284 # 06 Y:2007 | 06 | 2007 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $1,700 | $2,074 | Not Implemented |
LL0284 # 01 Y:2007 | 01 | 2007 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $52,170 | $49,000 | Not Implemented |
LL0284 # 05 Y:2007 | 05 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,314 | $2,100 | Not Implemented |
LL0284 # 02 Y:2007 | 02 | 2007 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $33,682 | $1,600 | Not Implemented |
LL0284 # 07 Y:2007 | 07 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,030 | $451 | Not Implemented |