IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,055

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LL0113 # 02 Y:2001 02 2001 INSULATE BARE EQUIPMENT $13,907 $845 Not Implemented
LL0113 # 03 Y:2001 03 2001 USE OPTIMUM THICKNESS INSULATION $62,646 $51,608 Not Implemented
LL0113 # 04 Y:2001 04 2001 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $23,727 $12,240 Not Implemented
LL0113 # 05 Y:2001 05 2001 USE PHOTOCELL CONTROLS $1,979 $203 Not Implemented
LL0125 # 01 Y:2001 01 2001 OPTIMIZE PLANT POWER FACTOR $766 $2,625 Implemented
LL0125 # 02 Y:2001 02 2001 USE PHOTOCELL CONTROLS $296 $71 Not Implemented
LL0125 # 03 Y:2001 03 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,327 $13,815 Implemented
LL0125 # 04 Y:2001 04 2001 INSULATE BARE EQUIPMENT $813 $915 Not Implemented
LL0125 # 05 Y:2001 05 2001 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $680 $0 Implemented
LL0125 # 06 Y:2001 06 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,602 $706 Implemented
LL0122 # 01 Y:2001 01 2001 INSTALL SKYLIGHTS $3,305 $1,737 Not Implemented
LL0122 # 02 Y:2001 02 2001 OPTIMIZE PLANT POWER FACTOR $113,313 $117,135 n/a
LL0122 # 03 Y:2001 03 2001 INSULATE BARE EQUIPMENT $5,071 $5,224 Not Implemented
LL0122 # 04 Y:2001 04 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,898 $660 Implemented
LL0122 # 05 Y:2001 05 2001 USE PHOTOCELL CONTROLS $8,786 $495 Implemented
LL0118 # 01 Y:2001 01 2001 OPTIMIZE PLANT POWER FACTOR $53,505 $55,889 Not Implemented
LL0118 # 02 Y:2001 02 2001 INSTALL OCCUPANCY SENSORS $10,056 $297 Implemented
LL0118 # 03 Y:2001 03 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,379 $2,190 Implemented
LL0118 # 04 Y:2001 04 2001 USE POWER DURING OFF-PEAK PERIODS $18,618 $0 Not Implemented
LL0118 # 05 Y:2001 05 2001 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $36,180 $0 Implemented
LL0118 # 06 Y:2001 06 2001 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $15,884 $456 Implemented
LL0119 # 01 Y:2001 01 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $22,921 $4,950 Implemented
LL0119 # 02 Y:2001 02 2001 INSULATE BARE EQUIPMENT $36,284 $19,204 Not Implemented
LL0119 # 03 Y:2001 03 2001 INSTALL SKYLIGHTS $8,387 $13,894 Not Implemented
LL0119 # 04 Y:2001 04 2001 OPTIMIZE PLANT POWER FACTOR $45,054 $173,974 Implemented