Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,083
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS2510 # 06 Y:2025 | 06 | 2025 | ADJUST BURNERS FOR EFFICIENT OPERATION | $62,919 | $100,000 | n/a |
LS2510 # 04 Y:2025 | 04 | 2025 | USE IN-PROCESS RECYCLING WHENEVER POSSIBLE | $24,480 | $14,000 | n/a |
LS2510 # 01 Y:2025 | 01 | 2025 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,765 | $200 | n/a |
LS2510 # 07 Y:2025 | 07 | 2025 | ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF | $2,760 | $4,900 | n/a |
LS2510 # 08 Y:2025 | 08 | 2025 | REPLACE BOILER | $14,158 | $66,000 | n/a |
LS2510 # 03 Y:2025 | 03 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,945 | $450 | n/a |
LS2510 # 05 Y:2025 | 05 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $28,682 | $21,000 | n/a |
LS2510 # 02 Y:2025 | 02 | 2025 | INSTALL TIMERS AND/OR THERMOSTATS | $287 | $50 | n/a |
LS2509 # 01 Y:2025 | 01 | 2025 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $40,834 | $25,000 | n/a |
LS2509 # 07 Y:2025 | 07 | 2025 | INSULATE BARE EQUIPMENT | $214,970 | $1,500,000 | n/a |
LS2509 # 04 Y:2025 | 04 | 2025 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $127,011 | $200,000 | n/a |
LS2509 # 05 Y:2025 | 05 | 2025 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,218 | $2,700 | n/a |
LS2509 # 02 Y:2025 | 02 | 2025 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $12,547 | $16,300 | n/a |
LS2509 # 03 Y:2025 | 03 | 2025 | IMPROVE PROCESS CONTROL TO PREVENT SPILLS OF MATERIAL | $56,956 | $80,000 | n/a |
LS2509 # 06 Y:2025 | 06 | 2025 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $53,529 | $144,549 | n/a |
LS2508 # 02 Y:2025 | 02 | 2025 | INSTALL SUB-METERING EQUIPMENT | $3,313 | $3,000 | n/a |
LS2508 # 01 Y:2025 | 01 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $771 | $675 | n/a |
LS2508 # 08 Y:2025 | 08 | 2025 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $8,663 | $48,183 | n/a |
LS2508 # 04 Y:2025 | 04 | 2025 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,488 | $5,190 | n/a |
LS2508 # 05 Y:2025 | 05 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $39,572 | $160,992 | n/a |
LS2508 # 03 Y:2025 | 03 | 2025 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $9,000 | $25,000 | n/a |
LS2508 # 07 Y:2025 | 07 | 2025 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,709 | $16,949 | n/a |
LS2508 # 06 Y:2025 | 06 | 2025 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,510 | $10,600 | n/a |
LS2507 # 03 Y:2025 | 03 | 2025 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $44,252 | $192,732 | n/a |
LS2507 # 04 Y:2025 | 04 | 2025 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $12,714 | $65,000 | n/a |