Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
913
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS2408 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,047 | $135 | n/a |
LS2408 # 02 Y:2024 | 02 | 2024 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $37,002 | $144,549 | n/a |
LS2408 # 03 Y:2024 | 03 | 2024 | REPLACE BOILER | $57,645 | $247,500 | n/a |
LS2406 # 03 Y:2024 | 03 | 2024 | ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS | $9,410 | $28,500 | n/a |
LS2406 # 02 Y:2024 | 02 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,468 | $750 | n/a |
LS2406 # 04 Y:2024 | 04 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,460 | $11,500 | n/a |
LS2406 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,003 | $50 | n/a |
LS0424 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,011 | $1,676 | n/a |
LS0424 # 02 Y:2024 | 02 | 2024 | INSTALL OCCUPANCY SENSORS | $1,937 | $200 | n/a |
LS0424 # 01 Y:2024 | 01 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $16,625 | $1,500 | n/a |
LS0324 # 02 Y:2024 | 02 | 2024 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $12,003 | $1,360 | n/a |
LS0324 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,954 | $13,620 | n/a |
LS0324 # 01 Y:2024 | 01 | 2024 | INSTALL OCCUPANCY SENSORS | $2,912 | $175 | n/a |
LS2405 # 04 Y:2024 | 04 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $44,207 | $25,301 | n/a |
LS2405 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $11,023 | $50 | n/a |
LS2405 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,417 | $135 | n/a |
LS2405 # 06 Y:2024 | 06 | 2024 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $129,015 | $600,000 | n/a |
LS2405 # 01 Y:2024 | 01 | 2024 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $3,278 | $0 | n/a |
LS2405 # 05 Y:2024 | 05 | 2024 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $155,225 | $550,000 | n/a |
LS0224 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,796 | $25 | n/a |
LS0224 # 03 Y:2024 | 03 | 2024 | RECOVER WASTE HEAT FROM EQUIPMENT | $17,495 | $20,000 | n/a |
LS0224 # 05 Y:2024 | 05 | 2024 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $175,678 | $600,000 | n/a |
LS0224 # 02 Y:2024 | 02 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $1,962 | $75 | n/a |
LS0224 # 04 Y:2024 | 04 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,104 | $1,413 | n/a |
LS0224 # 06 Y:2024 | 06 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $12,486 | $113,400 | n/a |