Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,004
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS1923 # 02 Y:2023 | 02 | 2023 | INSTALL OCCUPANCY SENSORS | $8,272 | $1,300 | Implemented |
LS1923 # 03 Y:2023 | 03 | 2023 | USE DOUBLE OR TRIPLE GLAZED WINDOWS TO MAINTAIN HIGHER RELATIVE HUMIDITY AND TO REDUCE HEAT LOSSES | $18,500 | $12,889 | Implemented |
LS1923 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,170 | $13,688 | Implemented |
LS1923 # 05 Y:2023 | 05 | 2023 | REPLACE BOILER | $4,808 | $10,080 | Implemented |
LS2319 # 01 Y:2023 | 01 | 2023 | USE A DIFFERENT OR RECYCLED RAW MATERIAL | $12,150 | $0 | Not Implemented |
LS2319 # 02 Y:2023 | 02 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $291 | $50 | Not Implemented |
LS2319 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,512 | $1,365 | Not Implemented |
LS2319 # 04 Y:2023 | 04 | 2023 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $307 | $230 | Implemented |
LS2319 # 05 Y:2023 | 05 | 2023 | USE OTHER WASTE CONCENTRATION METHODS | $34,000 | $200,000 | Not Implemented |
LS1823 # 01 Y:2023 | 01 | 2023 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $8,335 | $0 | Implemented |
LS1823 # 02 Y:2023 | 02 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $19,295 | $900 | Implemented |
LS1823 # 03 Y:2023 | 03 | 2023 | INSTALL OCCUPANCY SENSORS | $669 | $750 | Implemented |
LS1723 # 01 Y:2023 | 01 | 2023 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $12,310 | $0 | Implemented |
LS1723 # 02 Y:2023 | 02 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,341 | $0 | Implemented |
LS1723 # 03 Y:2023 | 03 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $251 | $0 | Implemented |
LS1723 # 04 Y:2023 | 04 | 2023 | INSTALL OCCUPANCY SENSORS | $817 | $350 | Not Implemented |
LS1723 # 05 Y:2023 | 05 | 2023 | REDUCE HEAT GAIN BY WINDOW TINTING | $2,045 | $2,688 | Implemented |
LS1723 # 06 Y:2023 | 06 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,787 | $15,377 | Implemented |
LS1723 # 07 Y:2023 | 07 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $43,453 | $429,000 | Not Implemented |
LS2318 # 04 Y:2023 | 04 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $17,311 | $43,200 | Implemented |
LS2318 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,605 | $90 | Implemented |
LS2318 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,425 | $372 | Implemented |
LS2318 # 03 Y:2023 | 03 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $14,825 | $3,000 | Not Implemented |
LS2317 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $344 | $45 | Implemented |
LS2317 # 02 Y:2023 | 02 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $223 | $50 | Implemented |