Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,692
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0255 # 07 Y:1992 | 07 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,985 | $900 | Implemented |
MA0255 # 08 Y:1992 | 08 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,734 | $360 | Implemented |
MA0255 # 09 Y:1992 | 09 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,209 | $0 | Implemented |
MA0255 # 10 Y:1992 | 10 | 1992 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $200 | $300 | Implemented |
MA0255 # 11 Y:1992 | 11 | 1992 | COVER OPEN TANKS | $181 | $285 | Not Implemented |
MA0251 # 01 Y:1992 | 01 | 1992 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $15,064 | $40,000 | Not Implemented |
MA0251 # 02 Y:1992 | 02 | 1992 | INSULATE BARE EQUIPMENT | $9,500 | $1,316 | Implemented |
MA0251 # 03 Y:1992 | 03 | 1992 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $5,623 | $2,472 | Implemented |
MA0251 # 04 Y:1992 | 04 | 1992 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,191 | $4,450 | Implemented |
MA0251 # 05 Y:1992 | 05 | 1992 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,099 | $2,050 | Implemented |
MA0251 # 06 Y:1992 | 06 | 1992 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,639 | $500 | Implemented |
MA0251 # 07 Y:1992 | 07 | 1992 | INSTALL SET-BACK TIMERS | $273 | $90 | Not Implemented |
MA0251 # 08 Y:1992 | 08 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $243 | $300 | Implemented |
MA0252 # 01 Y:1992 | 01 | 1992 | BURN A LESS EXPENSIVE GRADE OF FUEL | $152,380 | $100,000 | Implemented |
MA0252 # 02 Y:1992 | 02 | 1992 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $24,026 | $33,800 | Not Implemented |
MA0252 # 03 Y:1992 | 03 | 1992 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $17,456 | $55,777 | Not Implemented |
MA0252 # 04 Y:1992 | 04 | 1992 | RECOVER WASTE HEAT FROM EQUIPMENT | $8,460 | $4,239 | Not Implemented |
MA0252 # 05 Y:1992 | 05 | 1992 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $3,342 | $0 | Implemented |
MA0252 # 06 Y:1992 | 06 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,254 | $600 | Implemented |
MA0252 # 07 Y:1992 | 07 | 1992 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $969 | $3,289 | Not Implemented |
MA0253 # 01 Y:1992 | 01 | 1992 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,608 | $15,134 | Implemented |
MA0253 # 02 Y:1992 | 02 | 1992 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $22,977 | $5,000 | Implemented |
MA0253 # 03 Y:1992 | 03 | 1992 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $6,697 | $2,524 | Implemented |
MA0253 # 04 Y:1992 | 04 | 1992 | INSULATE BARE EQUIPMENT | $8,302 | $4,977 | Not Implemented |
MA0253 # 05 Y:1992 | 05 | 1992 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,078 | $2,000 | Implemented |