Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,929
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0379 # 01 Y:1996 | 01 | 1996 | USE A RAG RECYCLE SERVICE | $2,866 | $1,664 | Implemented |
MA0379 # 02 Y:1996 | 02 | 1996 | USE RADIANT HEATER FOR SPOT HEATING | $2,992 | $9,900 | Not Implemented |
MA0379 # 03 Y:1996 | 03 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $558 | $225 | Implemented |
MA0379 # 04 Y:1996 | 04 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $427 | $225 | Implemented |
MA0379 # 05 Y:1996 | 05 | 1996 | INSTALL EFFICIENT RECTIFIERS | $17,513 | $60,000 | Not Implemented |
MA0379 # 06 Y:1996 | 06 | 1996 | OPTIMIZE PLANT POWER FACTOR | $405 | $711 | Not Implemented |
MA0379 # 07 Y:1996 | 07 | 1996 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $541 | $1,750 | Not Implemented |
MA0378 # 01 Y:1996 | 01 | 1996 | INSULATE BARE EQUIPMENT | $6,197 | $3,178 | Not Implemented |
MA0378 # 02 Y:1996 | 02 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $413 | $272 | Not Implemented |
MA0378 # 03 Y:1996 | 03 | 1996 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,699 | $1,415 | Not Implemented |
MA0378 # 04 Y:1996 | 04 | 1996 | USE RADIANT HEATER FOR SPOT HEATING | $2,379 | $3,200 | Not Implemented |
MA0378 # 05 Y:1996 | 05 | 1996 | USE MAGNETIC TECHNOLOGY TO TREAT WATER | $3,300 | $9,235 | Not Implemented |
MA0376 # 01 Y:1996 | 01 | 1996 | USE EVAPORATION TO CONCENTRATE MATERIAL | $24,817 | $16,000 | Implemented |
MA0376 # 02 Y:1996 | 02 | 1996 | UTILIZE OXIDATION/REDUCTION FOR NEUTRALIZATION | $18,500 | $3,200 | Not Implemented |
MA0376 # 03 Y:1996 | 03 | 1996 | REDUCE VENTILATION AIR | $1,830 | $1,150 | Implemented |
MA0376 # 04 Y:1996 | 04 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,918 | $13,680 | Implemented |
MA0376 # 05 Y:1996 | 05 | 1996 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $450 | $516 | Implemented |
MA0371 # 01 Y:1996 | 01 | 1996 | RECOVER WASTE HEAT FROM EQUIPMENT | $71,639 | $68,000 | Not Implemented |
MA0371 # 02 Y:1996 | 02 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,504 | $0 | Implemented |
MA0371 # 03 Y:1996 | 03 | 1996 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $22,269 | $15,000 | Implemented |
MA0371 # 04 Y:1996 | 04 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $39,790 | $174,574 | Implemented |
MA0371 # 05 Y:1996 | 05 | 1996 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $1,688 | $2,508 | Not Implemented |
MA0369 # 01 Y:1996 | 01 | 1996 | ADOPT IN-HOUSE MATERIAL GENERATION | $21,886 | $11,000 | Implemented |
MA0369 # 02 Y:1996 | 02 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,735 | $49,531 | Not Implemented |
MA0369 # 03 Y:1996 | 03 | 1996 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $4,903 | $8,750 | Not Implemented |