Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,332
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MO0058 # 01 Y:1992 | 01 | 1992 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $1,554 | $300 | Not Implemented |
MO0058 # 02 Y:1992 | 02 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,522 | $700 | Not Implemented |
MO0058 # 03 Y:1992 | 03 | 1992 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,618 | $20 | Not Implemented |
MO0058 # 04 Y:1992 | 04 | 1992 | INSTALL SET-BACK TIMERS | $1,712 | $1,400 | Implemented |
MO0058 # 05 Y:1992 | 05 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $616 | $491 | Not Implemented |
MO0058 # 06 Y:1992 | 06 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $69 | $255 | Not Implemented |
MO0058 # 07 Y:1992 | 07 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $372 | $0 | Not Implemented |
MO0058 # 08 Y:1992 | 08 | 1992 | IMPROVE LUBRICATION PRACTICES | $828 | $240 | Implemented |
MO0058 # 09 Y:1992 | 09 | 1992 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $354 | $551 | Not Implemented |
MO0059 # 01 Y:1992 | 01 | 1992 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $2,446 | $300 | Not Implemented |
MO0059 # 02 Y:1992 | 02 | 1992 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $295 | $500 | Implemented |
MO0059 # 03 Y:1992 | 03 | 1992 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,545 | $20 | Not Implemented |
MO0059 # 04 Y:1992 | 04 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,167 | $395 | Implemented |
MO0059 # 05 Y:1992 | 05 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $536 | $96 | Implemented |
MO0059 # 06 Y:1992 | 06 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,670 | $10,000 | Implemented |
MO0059 # 07 Y:1992 | 07 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,316 | $630 | Implemented |
MO0059 # 08 Y:1992 | 08 | 1992 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $91 | $573 | Not Implemented |
MO0059 # 09 Y:1992 | 09 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $335 | $0 | Not Implemented |
MO0059 # 10 Y:1992 | 10 | 1992 | INSTALL TIMERS AND/OR THERMOSTATS | $7,318 | $2,638 | Not Implemented |
MO0059 # 11 Y:1992 | 11 | 1992 | RECOVER AND REUSE COOLING WATER | $528 | $0 | Not Implemented |
MO0060 # 01 Y:1992 | 01 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,173 | $775 | Implemented |
MO0060 # 02 Y:1992 | 02 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,452 | $2,832 | Implemented |
MO0060 # 03 Y:1992 | 03 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $962 | $2,230 | Implemented |
MO0060 # 04 Y:1992 | 04 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $322 | $0 | Implemented |
MO0060 # 05 Y:1992 | 05 | 1992 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,377 | $5,400 | Implemented |