Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
299
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OD0175 # 02 Y:2000 | 02 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $800 | $520 | Implemented |
OD0170 # 03 Y:2000 | 03 | 2000 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $642 | $726 | Implemented |
OD0170 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,359 | $5,892 | Implemented |
OD0169 # 06 Y:2000 | 06 | 2000 | PAY UTILITY BILLS ON TIME | $1,500 | $0 | Implemented |
OD0169 # 03 Y:2000 | 03 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $990 | $1,800 | Implemented |
OD0169 # 02 Y:2000 | 02 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $972 | $1,400 | Implemented |
OD0168 # 03 Y:2000 | 03 | 2000 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $319 | $250 | Implemented |
OD0168 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,584 | $4,191 | Implemented |
OD0165 # 06 Y:2000 | 06 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,026 | $2,400 | Implemented |
OD0165 # 05 Y:2000 | 05 | 2000 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $31,722 | $0 | Implemented |
OD0165 # 02 Y:2000 | 02 | 2000 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,597 | $560 | Implemented |
OD0163 # 02 Y:2000 | 02 | 2000 | USE SYNTHETIC LUBRICANT | $372 | $67 | Implemented |
OD0158 # 05 Y:2000 | 05 | 2000 | REPAIR OR REPLACE STEAM TRAPS | $20,642 | $4,920 | Implemented |
OD0157 # 03 Y:2000 | 03 | 2000 | REPAIR OR REPLACE STEAM TRAPS | $4,241 | $1,420 | Implemented |
OD0155 # 03 Y:2000 | 03 | 2000 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $450 | $179 | Implemented |
OD0155 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,185 | $26,708 | Implemented |
OD0156 # 03 Y:2000 | 03 | 2000 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $148 | $209 | Implemented |
OD0156 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,988 | $7,743 | Implemented |
OD0154 # 03 Y:2000 | 03 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $266 | $200 | Implemented |
OD0153 # 07 Y:2000 | 07 | 2000 | PAY BILLS ON TIME TO AVOID LATE FEES | $1,319 | $0 | Implemented |
OD0146 # 03 Y:1999 | 03 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $85 | $20 | Implemented |
OD0146 # 02 Y:1999 | 02 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $185 | $90 | Implemented |
OD0146 # 06 Y:1999 | 06 | 1999 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $643 | $0 | Implemented |
OD0145 # 04 Y:1999 | 04 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,396 | $220 | Implemented |
OD0145 # 03 Y:1999 | 03 | 1999 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,280 | $495 | Implemented |