IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

7,673

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK1015 # 02 Y:2019 02 2019 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $15,577 $17,500 Not Implemented
OK1015 # 03 Y:2019 03 2019 INSTALL SET-BACK TIMERS $320 $200 Implemented
OK1015 # 04 Y:2019 04 2019 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $380 $435 Not Implemented
OK1015 # 05 Y:2019 05 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $427 $2,045 Implemented
OK1014 # 01 Y:2019 01 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $29,926 $9,064 Implemented
OK1014 # 02 Y:2019 02 2019 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $3,114 $3,878 Implemented
OK1014 # 03 Y:2019 03 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,017 $1,750 Implemented
OK1013 # 01 Y:2019 01 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $11,284 $4,982 Implemented
OK1013 # 02 Y:2019 02 2019 TURN OFF EQUIPMENT WHEN NOT IN USE $14,945 $0 Not Implemented
OK1013 # 03 Y:2019 03 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $60,608 $35,153 Implemented
OK1013 # 04 Y:2019 04 2019 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $5,610 $6,480 Not Implemented
OK1013 # 05 Y:2019 05 2019 REPLACE TREATED WATER WITH WELL / SURFACE WATER $264,923 $206,847 Not Implemented
OK1013 # 06 Y:2019 06 2019 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $4,999 $4,520 Implemented
OK1012 # 01 Y:2019 01 2019 TURN OFF EQUIPMENT WHEN NOT IN USE $4,858 $0 Implemented
OK1012 # 02 Y:2019 02 2019 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $2,617 $1,676 Implemented
OK1012 # 03 Y:2019 03 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,564 $12,651 Implemented
OK1012 # 04 Y:2019 04 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,148 $1,560 Implemented
OK1012 # 05 Y:2019 05 2019 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $686 $405 Implemented
OK1012 # 06 Y:2019 06 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $262 $106 Not Implemented
OK1011 # 01 Y:2019 01 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,499 $1,898 Implemented
OK1011 # 02 Y:2019 02 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,528 $8,106 Not Implemented
OK1011 # 03 Y:2019 03 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,937 $15,573 Implemented
OK1011 # 04 Y:2019 04 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $43,176 $71,250 Implemented
OK1011 # 05 Y:2019 05 2019 OPTIMIZE PLANT POWER FACTOR $13,080 $57,161 Not Implemented
OK1011 # 06 Y:2019 06 2019 INSULATE BARE EQUIPMENT $5,110 $63 Not Implemented