IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

183

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0202 # 02 Y:2000 02 2000 INSTALL OCCUPANCY SENSORS $960 $600 Implemented
SF0202 # 04 Y:2000 04 2000 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $941 $5,000 Not Implemented
SF0202 # 03 Y:2000 03 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,800 $11,610 Not Implemented
SF0202 # 06 Y:2000 06 2000 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $11,715 $17,142 Not Implemented
SF0202 # 01 Y:2000 01 2000 TURN OFF EQUIPMENT WHEN NOT IN USE $698 $0 Implemented
SF0202 # 05 Y:2000 05 2000 $5,583 $2,180 Implemented
SF0200 # 01 Y:2000 01 2000 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $2,619 $2,800 Not Implemented
SF0200 # 04 Y:2000 04 2000 RECOVER AND REUSE WASTE MATERIAL $24,800 $0 Not Implemented
SF0200 # 03 Y:2000 03 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,122 $13,280 Not Implemented
SF0200 # 02 Y:2000 02 2000 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $2,726 $7,750 Not Implemented
SF0200 # 05 Y:2000 05 2000 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $16,728 $70,000 Not Implemented
SF0201 # 06 Y:2000 06 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,796 $8,825 Implemented
SF0201 # 02 Y:2000 02 2000 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,708 $25 Implemented
SF0201 # 03 Y:2000 03 2000 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $23,492 $19,738 Implemented
SF0201 # 09 Y:2000 09 2000 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $24,638 $18,750 Not Implemented
SF0201 # 07 Y:2000 07 2000 RECOVER AND REUSE WASTE MATERIAL $12,259 $7,650 Implemented
SF0201 # 04 Y:2000 04 2000 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $15,456 $15,452 Not Implemented
SF0201 # 05 Y:2000 05 2000 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $7,180 $11,750 Not Implemented
SF0201 # 01 Y:2000 01 2000 APPLY A PROTECTIVE COATING TO RACKS AND TANKS $4,646 $120 Implemented
SF0201 # 08 Y:2000 08 2000 RECOVER AND REUSE WASTE MATERIAL $1,635 $0 Implemented
SF0199 # 02 Y:2000 02 2000 MODERATE COOLING TOWER OUTLET TEMPERATURE $4,250 $850 Implemented
SF0199 # 05 Y:2000 05 2000 INSTALL OCCUPANCY SENSORS $1,079 $1,080 Implemented
SF0199 # 06 Y:2000 06 2000 INSTALL OCCUPANCY SENSORS $1,583 $2,000 Implemented
SF0199 # 04 Y:2000 04 2000 RECOVER MECHANICAL ENERGY $2,300 $345 Not Implemented
SF0199 # 01 Y:2000 01 2000 $584 $0 Implemented