Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
49
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SJ0008 # 06 Y:2023 | 06 | 2023 | INSTALL OCCUPANCY SENSORS | $78 | $177 | Not Implemented |
SJ0008 # 04 Y:2023 | 04 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $126 | $436 | Not Implemented |
SJ0008 # 03 Y:2023 | 03 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $80 | $0 | Not Implemented |
SJ0008 # 05 Y:2023 | 05 | 2023 | INSULATE BARE EQUIPMENT | $265 | $344 | Implemented |
SJ0008 # 02 Y:2023 | 02 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $365 | $0 | Implemented |
SJ0008 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $13,195 | $77,365 | Not Implemented |
SJ0007 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $128,947 | $765,487 | n/a |
SJ0007 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,271 | $13,090 | n/a |
SJ0007 # 08 Y:2023 | 08 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,635 | $0 | n/a |
SJ0007 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $951 | $495 | n/a |
SJ0007 # 04 Y:2023 | 04 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $192 | $0 | n/a |
SJ0007 # 05 Y:2023 | 05 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,529 | $0 | n/a |
SJ0007 # 06 Y:2023 | 06 | 2023 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $31,866 | $36,311 | n/a |
SJ0007 # 07 Y:2023 | 07 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $47,492 | $0 | n/a |
SJ0006 # 04 Y:2023 | 04 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,078 | $7,298 | n/a |
SJ0006 # 08 Y:2023 | 08 | 2023 | INSTALL / REPAIR INSULATION ON STEAM LINES | $332 | $1,762 | n/a |
SJ0006 # 07 Y:2023 | 07 | 2023 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $8,791 | $39,456 | n/a |
SJ0006 # 06 Y:2023 | 06 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,713 | $4,600 | n/a |
SJ0006 # 05 Y:2023 | 05 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $14,647 | $23,000 | n/a |
SJ0006 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $132,467 | $665,395 | n/a |
SJ0006 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $798 | $2,977 | n/a |
SJ0006 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,014 | $7,324 | n/a |
SJ0005 # 02 Y:2023 | 02 | 2023 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $23,445 | $5,613 | Not Implemented |
SJ0005 # 03 Y:2023 | 03 | 2023 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $270 | $0 | Not Implemented |
SJ0005 # 04 Y:2023 | 04 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,251 | $4,556 | Not Implemented |