Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
223
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0556 # 06 Y:1995 | 06 | 1995 | MODIFY MATERIAL APPLICATION METHODS | $205,755 | $81,770 | Implemented |
TN0556 # 01 Y:1995 | 01 | 1995 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $3,874 | $7,950 | Not Implemented |
TN0556 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $374 | $38 | Implemented |
TN0556 # 02 Y:1995 | 02 | 1995 | INSTALL SPECTRAL REFLECTORS / DELAMP | $4,587 | $18,500 | Not Implemented |
TN0556 # 03 Y:1995 | 03 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $660 | $1,240 | Not Implemented |
TN0556 # 05 Y:1995 | 05 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,298 | $0 | Not Implemented |
TN0555 # 09 Y:1995 | 09 | 1995 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $2,409 | $0 | Implemented |
TN0555 # 06 Y:1995 | 06 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $349 | $490 | Implemented |
TN0555 # 01 Y:1995 | 01 | 1995 | INSTALL TIMERS AND/OR THERMOSTATS | $3,355 | $2,320 | Implemented |
TN0555 # 08 Y:1995 | 08 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $586 | $442 | Implemented |
TN0555 # 07 Y:1995 | 07 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $323 | $435 | Implemented |
TN0555 # 04 Y:1995 | 04 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $818 | $620 | Implemented |
TN0555 # 05 Y:1995 | 05 | 1995 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $229 | $385 | Not Implemented |
TN0555 # 03 Y:1995 | 03 | 1995 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,689 | $0 | Implemented |
TN0555 # 02 Y:1995 | 02 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $805 | $2,200 | Implemented |
TN0554 # 01 Y:1995 | 01 | 1995 | INSTALL SPECTRAL REFLECTORS / DELAMP | $5,277 | $19,760 | Not Implemented |
TN0554 # 05 Y:1995 | 05 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $431 | $990 | Not Implemented |
TN0554 # 04 Y:1995 | 04 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $343 | $820 | Not Implemented |
TN0554 # 03 Y:1995 | 03 | 1995 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $1,379 | $3,800 | Implemented |
TN0554 # 07 Y:1995 | 07 | 1995 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $1,046 | $0 | Not Implemented |
TN0554 # 02 Y:1995 | 02 | 1995 | INSTALL TIMERS AND/OR THERMOSTATS | $2,636 | $680 | Implemented |
TN0554 # 06 Y:1995 | 06 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,625 | $0 | Implemented |
TN0553 # 04 Y:1995 | 04 | 1995 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $14,284 | $20,800 | Not Implemented |
TN0553 # 03 Y:1995 | 03 | 1995 | INSTALL SPECTRAL REFLECTORS / DELAMP | $853 | $0 | Implemented |
TN0553 # 02 Y:1995 | 02 | 1995 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $3,313 | $1,320 | Implemented |