Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
251
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0253 # 06 Y:1995 | 06 | 1995 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $1,958 | $0 | n/a |
WI0253 # 04 Y:1995 | 04 | 1995 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $2,365 | $7,000 | n/a |
WI0253 # 02 Y:1995 | 02 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,306 | $7,683 | n/a |
WI0253 # 09 Y:1995 | 09 | 1995 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $2,860 | $0 | n/a |
WI0253 # 07 Y:1995 | 07 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $540 | $960 | n/a |
WI0253 # 05 Y:1995 | 05 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,029 | $2,000 | n/a |
WI0253 # 08 Y:1995 | 08 | 1995 | INSULATE BARE EQUIPMENT | $369 | $49 | n/a |
WI0253 # 03 Y:1995 | 03 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,174 | $0 | n/a |
WI0253 # 01 Y:1995 | 01 | 1995 | TURN OFF EQUIPMENT WHEN NOT IN USE | $6,770 | $0 | n/a |
WI0255 # 04 Y:1995 | 04 | 1995 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $2,521 | $0 | n/a |
WI0255 # 06 Y:1995 | 06 | 1995 | REDUCE AIR CONDITIONING LOAD BY EVAPORATING WATER FROM ROOF | $1,281 | $3,600 | n/a |
WI0255 # 10 Y:1995 | 10 | 1995 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $5,100 | $0 | n/a |
WI0255 # 09 Y:1995 | 09 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $615 | $0 | n/a |
WI0255 # 02 Y:1995 | 02 | 1995 | INSTALL OCCUPANCY SENSORS | $1,141 | $300 | n/a |
WI0255 # 08 Y:1995 | 08 | 1995 | USE OPTIMUM THICKNESS INSULATION | $671 | $1,067 | n/a |
WI0255 # 03 Y:1995 | 03 | 1995 | SHUT OFF AIR CONDITIONING IN WINTER HEATING SEASON | $2,897 | $6,500 | n/a |
WI0255 # 05 Y:1995 | 05 | 1995 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,060 | $0 | n/a |
WI0255 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,156 | $4,639 | n/a |
WI0255 # 11 Y:1995 | 11 | 1995 | RECOVER AND REUSE WASTE MATERIAL | $1,150 | $0 | n/a |
WI0255 # 07 Y:1995 | 07 | 1995 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $808 | $950 | n/a |
WI0249 # 04 Y:1995 | 04 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,153 | $250 | Implemented |
WI0249 # 05 Y:1995 | 05 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $488 | $97 | Not Implemented |
WI0249 # 02 Y:1995 | 02 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,781 | $150 | Not Implemented |
WI0249 # 06 Y:1995 | 06 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $359 | $0 | Not Implemented |
WI0249 # 01 Y:1995 | 01 | 1995 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,906 | $4,500 | Not Implemented |