IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 1995 |
Principal Product | X-Ray Tubes |
NAICS | n/a |
SIC | 3844 - X-ray Apparatus And Tubes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 300,000 |
Annual Production | 6,000 Pieces |
Production Hrs. Annual | 4,250 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $307,587 | 4,973,916 | kWh | $0.06 |
Natural Gas | $49,587 | 17,663 | MMBtu | $2.81 |
TOTAL ENERGY COSTS | $364,774 | |||
RECOMMENDED SAVINGS* | $22,371 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Natural Gas | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $6,770 Cost: - |
- | - | $6,770 | 2,765 | - | - |
- - kWh |
$6,770 2,765 MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,306 Cost: $7,683 |
$3,306 | 53,634 | - | - | - | - |
$3,306 53,634 kWh |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $2,174 Cost: - |
$2,174 | 35,170 | - | - | - | - |
$2,174 35,170 kWh |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE |
Savings: $2,365 Cost: $7,000 |
$2,365 | 38,394 | - | - | - | - |
$2,365 38,394 kWh |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $2,029 Cost: $2,000 |
$2,029 | 32,825 | - | - | - | - |
$2,029 32,825 kWh |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $1,958 Cost: - |
$3,460 | 41,911 | $(-1,502) | (-534) | - | - |
$3,460 41,911 kWh |
$(-1,502) (-534) MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $540 Cost: $960 |
$540 | 8,792 | - | - | - | - |
$540 8,792 kWh |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $369 Cost: $49 |
$369 | 5,862 | - | - | - | - |
$369 5,862 kWh |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $2,860 Cost: - |
- | - | - | - | $2,860 | 60,000 |
- - kWh |
- - MMBtu |
$2,860 60,000 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $22,371 Cost: $17,692 |
$14,243 | 216,588 | $5,268 | 2,231 | $2,860 | 60,000 | $14,243 216,588 kWh |
$5,268 2,231 MMBtu |
$2,860 60,000 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - MMBtu |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Natural Gas | Solid Waste (non-haz) |