IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

188

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WI0503 # 05 Y:2005 05 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,506 $0 Not Implemented
WI0503 # 02 Y:2005 02 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $11,209 $21,960 Not Implemented
WI0503 # 04 Y:2005 04 2005 RECOVER WASTE HEAT FROM EQUIPMENT $5,112 $1,000 Not Implemented
WI0503 # 07 Y:2005 07 2005 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,742 $4,900 Not Implemented
WI0503 # 06 Y:2005 06 2005 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,350 $640 Not Implemented
WI0503 # 01 Y:2005 01 2005 IMPROVE SPACE COMFORT CONDITIONING $47,772 $9,625 Not Implemented
WI0503 # 03 Y:2005 03 2005 USE OPTIMUM THICKNESS INSULATION $8,005 $7,500 Not Implemented
WI0502 # 01 Y:2005 01 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,862 $27,000 Not Implemented
WI0502 # 08 Y:2005 08 2005 IMPROVE LUBRICATION PRACTICES $1,579 $1,238 Not Implemented
WI0502 # 09 Y:2005 09 2005 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,524 $1,280 Not Implemented
WI0502 # 07 Y:2005 07 2005 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $2,670 $520 Not Implemented
WI0502 # 04 Y:2005 04 2005 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $3,880 $0 Not Implemented
WI0502 # 03 Y:2005 03 2005 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $3,880 $0 Not Implemented
WI0502 # 02 Y:2005 02 2005 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $4,177 $9,500 Not Implemented
WI0502 # 10 Y:2005 10 2005 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED $1,374 $1,500 Not Implemented
WI0502 # 05 Y:2005 05 2005 INSTALL TIMERS AND/OR THERMOSTATS $2,699 $0 Not Implemented
WI0502 # 06 Y:2005 06 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,919 $0 Not Implemented
WI0501 # 04 Y:2005 04 2005 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $3,873 $0 Not Implemented
WI0501 # 06 Y:2005 06 2005 USE SYNTHETIC LUBRICANT $921 $800 Not Implemented
WI0501 # 03 Y:2005 03 2005 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,905 $0 Not Implemented
WI0501 # 01 Y:2005 01 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,224 $19,800 Not Implemented
WI0501 # 05 Y:2005 05 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,008 $0 Not Implemented
WI0501 # 02 Y:2005 02 2005 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $16,037 $30,800 Not Implemented
WI0500 # 06 Y:2005 06 2005 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $2,252 $2,032 n/a
WI0500 # 01 Y:2005 01 2005 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $57,577 $25,000 n/a