Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,052
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UK2001 # 03 Y:2020 | 03 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,887 | $9,378 | Implemented |
UK2001 # 01 Y:2020 | 01 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,076 | $2,010 | Implemented |
UK2001 # 07 Y:2020 | 07 | 2020 | CLEAN CONDENSER TUBES | $4,023 | $8,700 | Implemented |
UK1913 # 07 Y:2019 | 07 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,770 | $32,561 | Implemented |
UK1913 # 06 Y:2019 | 06 | 2019 | INSTALL OCCUPANCY SENSORS | $333 | $1,120 | Implemented |
UK1913 # 04 Y:2019 | 04 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,111 | $550 | Implemented |
UK1913 # 03 Y:2019 | 03 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,642 | $2,520 | Implemented |
UK1913 # 01 Y:2019 | 01 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $15,855 | $2,510 | Implemented |
UK1913 # 10 Y:2019 | 10 | 2019 | OPTIMIZE PLANT POWER FACTOR | $15,097 | $10,570 | Implemented |
UK1913 # 08 Y:2019 | 08 | 2019 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $243 | $127 | Implemented |
UK1912 # 09 Y:2019 | 09 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $86,767 | $5,000 | Implemented |
UK1912 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,364 | $30,555 | Implemented |
UK1912 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $28,487 | $2,150 | Implemented |
UK1912 # 02 Y:2019 | 02 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $10,541 | $0 | Implemented |
UK1911 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,273 | $24,987 | Implemented |
UK1911 # 01 Y:2019 | 01 | 2019 | OPTIMIZE PLANT POWER FACTOR | $45,696 | $27,825 | Implemented |
UK1911 # 04 Y:2019 | 04 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,363 | $700 | Implemented |
UK1911 # 05 Y:2019 | 05 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,560 | $3,950 | Implemented |
UK1910 # 07 Y:2019 | 07 | 2019 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $838 | $350 | Implemented |
UK1910 # 06 Y:2019 | 06 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $569 | $300 | Implemented |
UK1910 # 05 Y:2019 | 05 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $65,342 | $110,141 | Implemented |
UK1910 # 04 Y:2019 | 04 | 2019 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $4,283 | $0 | Implemented |
UK1910 # 03 Y:2019 | 03 | 2019 | INSULATE BARE EQUIPMENT | $280 | $161 | Implemented |
UK1910 # 02 Y:2019 | 02 | 2019 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $510 | $1,775 | Implemented |
UK1910 # 01 Y:2019 | 01 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,415 | $2,477 | Implemented |