Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,142
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0008 # 03 Y:2007 | 03 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,289 | $800 | Implemented |
MZ0008 # 04 Y:2007 | 04 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $694 | $1,300 | Implemented |
MZ0008 # 05 Y:2007 | 05 | 2007 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $812 | $0 | Implemented |
MZ0008 # 06 Y:2007 | 06 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $22 | $23 | Implemented |
MZ0007 # 01 Y:2007 | 01 | 2007 | COVER OPEN TANKS | $2,560 | $0 | Implemented |
MZ0007 # 03 Y:2007 | 03 | 2007 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $533 | $0 | Implemented |
MZ0007 # 04 Y:2007 | 04 | 2007 | DISCONNECT BALLASTS | $27,567 | $1,310 | Implemented |
MZ0007 # 05 Y:2007 | 05 | 2007 | INSTALL OCCUPANCY SENSORS | $5,535 | $3,250 | Implemented |
MZ0004 # 01 Y:2007 | 01 | 2007 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,138 | $2,230 | Implemented |
MZ0004 # 04 Y:2007 | 04 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $184 | $150 | Implemented |
MZ0004 # 09 Y:2007 | 09 | 2007 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $4,600 | $0 | Implemented |
MZ0002 # 03 Y:2007 | 03 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $40,930 | $40,700 | Implemented |
MZ0001 # 02 Y:2007 | 02 | 2007 | Hardware | $75,000 | $78,000 | Implemented |
MZ0001 # 03 Y:2007 | 03 | 2007 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $3,400 | $800 | Implemented |
MZ0001 # 05 Y:2007 | 05 | 2007 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,915 | $3,300 | Implemented |
BD0316 # 02 Y:2006 | 02 | 2006 | COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER | $4,724 | $1,200 | Implemented |
BD0316 # 03 Y:2006 | 03 | 2006 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $13,153 | $8,363 | Implemented |
BD0316 # 04 Y:2006 | 04 | 2006 | INSTALL OCCUPANCY SENSORS | $1,033 | $675 | Implemented |
BD0316 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $679 | $2,102 | Implemented |
BD0313 # 01 Y:2006 | 01 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $180,015 | $152 | Implemented |
BD0313 # 02 Y:2006 | 02 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $12,962 | $5,000 | Implemented |
BD0313 # 04 Y:2006 | 04 | 2006 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $13,938 | $0 | Implemented |
BD0313 # 05 Y:2006 | 05 | 2006 | INSTALL TURBULATORS | $2,094 | $1,500 | Implemented |
BD0313 # 07 Y:2006 | 07 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,780 | $800 | Implemented |
BD0313 # 08 Y:2006 | 08 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,038 | $10,039 | Implemented |