Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,875
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0229 # 13 Y:2006 | 13 | 2006 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $372 | $845 | Not Implemented |
SU0229 # 14 Y:2006 | 14 | 2006 | INSULATE BARE EQUIPMENT | $781 | $2,198 | Not Implemented |
MA0594 # 01 Y:2006 | 01 | 2006 | INSTALL TIMERS AND/OR THERMOSTATS | $123,147 | $15,525 | Implemented |
MA0594 # 02 Y:2006 | 02 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $49,354 | $121,835 | Implemented |
MA0594 # 03 Y:2006 | 03 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $40,484 | $141,413 | Not Implemented |
MA0594 # 04 Y:2006 | 04 | 2006 | REPAIR OR REPLACE STEAM TRAPS | $11,241 | $7,665 | Not Implemented |
MA0594 # 05 Y:2006 | 05 | 2006 | REDUCE VENTILATION AIR | $5,860 | $3,505 | Implemented |
MA0594 # 06 Y:2006 | 06 | 2006 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $4,046 | $0 | Implemented |
MA0594 # 07 Y:2006 | 07 | 2006 | INSULATE BARE EQUIPMENT | $3,159 | $5,681 | Not Implemented |
MA0594 # 08 Y:2006 | 08 | 2006 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $2,600 | $500 | Not Implemented |
SU0227 # 01 Y:2006 | 01 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,070 | $0 | Not Implemented |
SU0227 # 02 Y:2006 | 02 | 2006 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $434 | $0 | Implemented |
SU0227 # 03 Y:2006 | 03 | 2006 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $209 | $0 | Not Implemented |
SU0227 # 04 Y:2006 | 04 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $13,581 | $2,035 | Not Implemented |
SU0227 # 05 Y:2006 | 05 | 2006 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $11,968 | $1,970 | Not Implemented |
SU0227 # 06 Y:2006 | 06 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,737 | $496 | Not Implemented |
SU0227 # 07 Y:2006 | 07 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $629 | $228 | Implemented |
SU0227 # 08 Y:2006 | 08 | 2006 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $2,257 | $1,220 | Not Implemented |
SU0227 # 09 Y:2006 | 09 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $725 | $1,187 | Implemented |
SU0227 # 10 Y:2006 | 10 | 2006 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $607 | $1,187 | Not Implemented |
SU0227 # 11 Y:2006 | 11 | 2006 | INSTALL OCCUPANCY SENSORS | $91 | $194 | Implemented |
SU0227 # 12 Y:2006 | 12 | 2006 | OPTIMIZE PLANT POWER FACTOR | $1,520 | $13,971 | Not Implemented |
SU0224 # 01 Y:2006 | 01 | 2006 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $11,943 | $0 | Implemented |
SU0224 # 02 Y:2006 | 02 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,147 | $0 | Implemented |
SU0224 # 03 Y:2006 | 03 | 2006 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,039 | $0 | Implemented |