Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,682
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0265 # 02 Y:2022 | 02 | 2022 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $705 | $304 | Implemented |
IC0265 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,312 | $7,533 | Implemented |
IC0265 # 04 Y:2022 | 04 | 2022 | ELIMINATE COMBUSTIBLE GAS IN FLUE GAS | $19,650 | $2,435 | Not Implemented |
IC0263 # 01 Y:2022 | 01 | 2022 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $32,000 | $174,422 | Implemented |
IC0263 # 02 Y:2022 | 02 | 2022 | REPLACE BOILER | $4,029 | $54,022 | Implemented |
IC0263 # 03 Y:2022 | 03 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,790 | $4,197 | Not Implemented |
IC0263 # 04 Y:2022 | 04 | 2022 | INSTALL OCCUPANCY SENSORS | $166 | $280 | Implemented |
IC0262 # 01 Y:2022 | 01 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,327 | $4,150 | Not Implemented |
IC0262 # 02 Y:2022 | 02 | 2022 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $356 | $5,338 | Not Implemented |
IC0262 # 03 Y:2022 | 03 | 2022 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,351 | $33,110 | Not Implemented |
IC0261 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,140 | $789 | Implemented |
IC0261 # 02 Y:2022 | 02 | 2022 | REPAIR AND ELIMINATE STEAM LEAKS | $4,207 | $360 | Implemented |
IC0261 # 03 Y:2022 | 03 | 2022 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,477 | $1,392 | Implemented |
IC0261 # 04 Y:2022 | 04 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,943 | $22,735 | Implemented |
IC0261 # 05 Y:2022 | 05 | 2022 | METER WASTE WATER | $695 | $600 | Implemented |
WM0178 # 06 Y:2022 | 06 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $120 | $500 | Not Implemented |
WM0178 # 05 Y:2022 | 05 | 2022 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $139 | $0 | Implemented |
WM0178 # 04 Y:2022 | 04 | 2022 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $154 | $0 | Implemented |
WM0178 # 03 Y:2022 | 03 | 2022 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $189 | $0 | Implemented |
WM0178 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $404 | $2,564 | Implemented |
WM0178 # 01 Y:2022 | 01 | 2022 | USE SYNTHETIC LUBRICANT | $4,241 | $8,000 | Not Implemented |
IC0260 # 01 Y:2022 | 01 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,208 | $1,715 | Not Implemented |
IC0260 # 02 Y:2022 | 02 | 2022 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $3,139 | $0 | Not Implemented |
IC0260 # 03 Y:2022 | 03 | 2022 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,387 | $3,452 | Not Implemented |
IC0260 # 04 Y:2022 | 04 | 2022 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,800 | $0 | Not Implemented |