Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,091
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0202 # 01 Y:1991 | 01 | 1991 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $458 | $1,012 | Implemented |
MA0202 # 02 Y:1991 | 02 | 1991 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $2,469 | $2,800 | Implemented |
MA0202 # 03 Y:1991 | 03 | 1991 | INSULATE BARE EQUIPMENT | $196 | $0 | Implemented |
MA0202 # 04 Y:1991 | 04 | 1991 | REDUCE HEAT GAIN BY WINDOW TINTING | $9,467 | $37,380 | Implemented |
TN0418 # 01 Y:1991 | 01 | 1991 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $10,212 | $1,840 | Implemented |
TN0418 # 02 Y:1991 | 02 | 1991 | KEEP LAMPS AND REFLECTORS CLEAN | $8,262 | $0 | Implemented |
TN0418 # 03 Y:1991 | 03 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $710 | $628 | Implemented |
TN0418 # 04 Y:1991 | 04 | 1991 | CLOSE OFF UNNEEDED STEAM LINES | $762 | $0 | Implemented |
TN0418 # 05 Y:1991 | 05 | 1991 | INSTALL SET-BACK TIMERS | $3,562 | $0 | Implemented |
TN0418 # 06 Y:1991 | 06 | 1991 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $399 | $0 | Implemented |
TN0418 # 07 Y:1991 | 07 | 1991 | USE MINIMUM STEAM OPERATING PRESSURE | $319 | $0 | Implemented |
TN0418 # 08 Y:1991 | 08 | 1991 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,254 | $0 | Implemented |
TN0418 # 09 Y:1991 | 09 | 1991 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $122 | $25 | Implemented |
TN0418 # 10 Y:1991 | 10 | 1991 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $69 | $0 | Implemented |
TN0418 # 11 Y:1991 | 11 | 1991 | INSULATE BARE EQUIPMENT | $62 | $146 | Implemented |
TN0418 # 12 Y:1991 | 12 | 1991 | INSTALL SET-BACK TIMERS | $200 | $410 | Implemented |