Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
6,055
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0237 # 03 Y:1995 | 03 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,737 | $0 | Implemented |
WI0237 # 04 Y:1995 | 04 | 1995 | SCHEDULE ROUTINE MAINTENANCE DURING NON-OPERATING PERIODS | $609 | $0 | Implemented |
WI0237 # 05 Y:1995 | 05 | 1995 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,102 | $1,000 | Not Implemented |
WI0237 # 06 Y:1995 | 06 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,662 | $1,280 | Not Implemented |
WI0237 # 07 Y:1995 | 07 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $902 | $0 | Implemented |
TN0562 # 01 Y:1995 | 01 | 1995 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,813 | $4,640 | Not Implemented |
TN0562 # 02 Y:1995 | 02 | 1995 | REPAIR AND ELIMINATE STEAM LEAKS | $4,419 | $450 | Implemented |
TN0562 # 03 Y:1995 | 03 | 1995 | CLOSE OFF UNNEEDED STEAM LINES | $1,156 | $0 | Not Implemented |
TN0562 # 04 Y:1995 | 04 | 1995 | USE MINIMUM STEAM OPERATING PRESSURE | $1,139 | $0 | Not Implemented |
TN0562 # 05 Y:1995 | 05 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,209 | $2,000 | Not Implemented |
TN0562 # 06 Y:1995 | 06 | 1995 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,231 | $0 | Implemented |
TN0562 # 07 Y:1995 | 07 | 1995 | INSULATE BARE EQUIPMENT | $152 | $60 | Implemented |
TN0562 # 08 Y:1995 | 08 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $963 | $530 | Implemented |
TN0562 # 09 Y:1995 | 09 | 1995 | RECOVER AND REUSE WASTE MATERIAL | $26,496 | $26,600 | Implemented |
TN0562 # 10 Y:1995 | 10 | 1995 | RECOVER AND REUSE WASTE MATERIAL | $13,248 | $26,200 | Not Implemented |
TN0562 # 11 Y:1995 | 11 | 1995 | IMPROVE HANDLING PRACTICES | $45,080 | $25,000 | Implemented |
TN0562 # 12 Y:1995 | 12 | 1995 | USE FILTER AND DRYING OVEN TO REDUCE SLUDGE VOLUME | $50,142 | $23,600 | Not Implemented |
UD0457 # 01 Y:1995 | 01 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,868 | $200 | Implemented |
UD0457 # 02 Y:1995 | 02 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,446 | $0 | Implemented |
UD0457 # 03 Y:1995 | 03 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $612 | $2,000 | Not Implemented |
UD0457 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $687 | $1,625 | Implemented |
UL0123 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,971 | $1,994 | Not Implemented |
UL0123 # 02 Y:1995 | 02 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,638 | $80 | Not Implemented |
UL0123 # 03 Y:1995 | 03 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,547 | $3,250 | Not Implemented |
HO0101 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,358 | $1,285 | Implemented |