Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,263
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS2213 # 02 Y:2022 | 02 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $704 | $38 | Implemented |
LS2213 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,162 | $360 | Implemented |
LS2213 # 04 Y:2022 | 04 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $32,208 | $7,144 | Implemented |
LS2213 # 05 Y:2022 | 05 | 2022 | USE PHOTOCELL CONTROLS | $1,557 | $370 | Implemented |
LS0722 # 01 Y:2022 | 01 | 2022 | INSTALL OCCUPANCY SENSORS | $8,954 | $400 | Implemented |
LS0722 # 02 Y:2022 | 02 | 2022 | USE PHOTOCELL CONTROLS | $3,937 | $481 | Not Implemented |
LS0722 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $37,161 | $8,927 | Implemented |
LS0722 # 04 Y:2022 | 04 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $155 | $38 | Implemented |
LS0622 # 01 Y:2022 | 01 | 2022 | INSTALL OCCUPANCY SENSORS | $17,059 | $500 | Implemented |
LS0622 # 02 Y:2022 | 02 | 2022 | USE PHOTOCELL CONTROLS | $9,454 | $999 | Not Implemented |
LS0622 # 03 Y:2022 | 03 | 2022 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,264 | $240 | Not Implemented |
LS0622 # 04 Y:2022 | 04 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $74,562 | $14,625 | Implemented |
LS0622 # 05 Y:2022 | 05 | 2022 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $684 | $660 | Implemented |
LS0622 # 06 Y:2022 | 06 | 2022 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $3,815 | $17,858 | Not Implemented |
LS0522 # 01 Y:2022 | 01 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $1,249 | $38 | Implemented |
LS0522 # 02 Y:2022 | 02 | 2022 | INSTALL OCCUPANCY SENSORS | $57 | $25 | Implemented |
LS0522 # 03 Y:2022 | 03 | 2022 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $125 | $80 | Not Implemented |
LS0522 # 04 Y:2022 | 04 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,124 | $3,917 | Implemented |
LS0422 # 01 Y:2022 | 01 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $7,800 | $0 | Implemented |
LS0422 # 02 Y:2022 | 02 | 2022 | USE PHOTOCELL CONTROLS | $1,326 | $74 | Implemented |
LS0422 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,012 | $135 | Not Implemented |
LS0422 # 04 Y:2022 | 04 | 2022 | INSTALL OCCUPANCY SENSORS | $496 | $250 | Implemented |
LS0422 # 05 Y:2022 | 05 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,312 | $11,682 | Implemented |
LS0422 # 06 Y:2022 | 06 | 2022 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $90 | $165 | Implemented |
LS0422 # 07 Y:2022 | 07 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $13 | $38 | Not Implemented |