Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Louisiana State University |
---|---|
Assessment Year | 2023 |
Principal Product | Wastewater Treatment |
NAICS | 221320 - Sewage Treatment Facilities |
SIC | 4952 - Sewerage Systems |
Sales | <$500,000 |
# of Employees | 40 |
Plant Area (Sq.Ft.) | 720,000 |
Annual Production | 3,660,000 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | LA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,349,525 | 19,371,200 | kWh | $0.07 |
Electricity Demand | $424,386 | 41,728 | kW-months/year | $10.17 |
Natural Gas | $239,485 | 32,626 | MMBtu | $7.34 |
TOTAL ENERGY COSTS | $2,013,396 | |||
RECOMMENDED SAVINGS* | $151,510 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $18,486 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $133,024 Cost: $41,910 |
$133,024 | 1,900,339 | - | - |
$133,024 1,900,339 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,461 Cost: $3,167 |
$3,373 | 48,180 | $1,088 | 107 |
$3,373 48,180 kWh |
$1,088 107 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $158 Cost: $125 |
$158 | 2,264 | - | - |
$158 2,264 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $13,867 Cost: $56,400 |
$13,867 | 198,108 | - | - |
$13,867 198,108 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $151,510 Cost: $101,602 |
$150,422 | 2,148,891 | $1,088 | 107 | $150,422 2,148,891 kWh |
$1,088 107 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $18,486 Cost: $59,692 |
$17,398 | 248,552 | $1,088 | 107 | $17,398 248,552 kWh |
$1,088 107 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand |