Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
161
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0232 # 01 Y:1999 | 01 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $192,386 | $82,242 | Not Implemented |
UF0232 # 02 Y:1999 | 02 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $8,006 | $60 | Implemented |
UF0232 # 03 Y:1999 | 03 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $5,521 | $1,500 | Implemented |
UF0232 # 04 Y:1999 | 04 | 1999 | INSTALL OCCUPANCY SENSORS | $1,539 | $834 | Implemented |
UF0232 # 05 Y:1999 | 05 | 1999 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $3,215 | $0 | Implemented |
UF0231 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,328 | $4,141 | Not Implemented |
UF0231 # 02 Y:1999 | 02 | 1999 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,140 | $2,650 | Not Implemented |
UF0231 # 03 Y:1999 | 03 | 1999 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,596 | $450 | Implemented |
UF0231 # 04 Y:1999 | 04 | 1999 | USE WASTE HEAT FROM HOT FLUE GASES TO GENERATE STEAM | $12,394 | $42,085 | Not Implemented |
UF0231 # 05 Y:1999 | 05 | 1999 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,198 | $1,000 | Implemented |
UF0231 # 06 Y:1999 | 06 | 1999 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $62,712 | $2,200 | Not Implemented |
UF0231 # 07 Y:1999 | 07 | 1999 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $1,200 | $0 | Implemented |
UF0231 # 08 Y:1999 | 08 | 1999 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $1,562 | $0 | Implemented |
UF0230 # 03 Y:1999 | 03 | 1999 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $9,804 | $8,987 | Not Implemented |
UF0230 # 02 Y:1999 | 02 | 1999 | INSTALL OCCUPANCY SENSORS | $1,142 | $2,240 | Not Implemented |
UF0230 # 01 Y:1999 | 01 | 1999 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $15,087 | $50 | Implemented |
UF0230 # 04 Y:1999 | 04 | 1999 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $3,916 | $0 | Not Implemented |
UF0230 # 05 Y:1999 | 05 | 1999 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $198 | $280 | Not Implemented |
UF0228 # 06 Y:1999 | 06 | 1999 | HIRE ADDITIONAL PERSONNEL TO REDUCE CHANGEOUT TIME | $57,600 | $1,090,000 | Implemented |
UF0228 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,851 | $0 | Not Implemented |
UF0228 # 02 Y:1999 | 02 | 1999 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,958 | $0 | Not Implemented |
UF0228 # 03 Y:1999 | 03 | 1999 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $9,888 | $50 | Implemented |
UF0228 # 04 Y:1999 | 04 | 1999 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $1,660 | $955 | Not Implemented |
UF0228 # 05 Y:1999 | 05 | 1999 | INSTALL EQUIPMENT TO MOVE PRODUCT | $274,473 | $22,390 | Not Implemented |
UF0226 # 02 Y:1999 | 02 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,196 | $0 | Not Implemented |