Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,032
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1095 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $35,046 | $25,523 | Implemented |
OK1093 # 13 Y:2023 | 13 | 2023 | MAKE A NEW BY-PRODUCT | $1,221,405 | $1,600,000 | Implemented |
OK1093 # 12 Y:2023 | 12 | 2023 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $150,722 | $300,000 | Implemented |
OK1093 # 11 Y:2023 | 11 | 2023 | CHANGE METHOD OF DEIONIZED WATER PRODUCTION | $98,980 | $367,077 | Implemented |
OK1093 # 10 Y:2023 | 10 | 2023 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $31,034 | $19,400 | Not Implemented |
OK1093 # 09 Y:2023 | 09 | 2023 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $4,201 | $632 | Not Implemented |
OK1093 # 08 Y:2023 | 08 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $12,354 | $1,420 | Implemented |
OK1093 # 07 Y:2023 | 07 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,345 | $8,534 | Implemented |
OK1093 # 06 Y:2023 | 06 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,010 | $0 | Implemented |
OK1093 # 05 Y:2023 | 05 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,087 | $343 | Implemented |
OK1093 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,723 | $1,260 | Implemented |
OK1093 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $29,830 | $374,400 | Implemented |
OK1093 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $420 | $900 | Implemented |
OK1093 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,678 | $10,052 | Implemented |
MZ0348 # 07 Y:2023 | 07 | 2023 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $2,203 | $4,132 | Not Implemented |
MZ0348 # 06 Y:2023 | 06 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,751 | $5,386 | Implemented |
MZ0348 # 05 Y:2023 | 05 | 2023 | INSTALL OCCUPANCY SENSORS | $3,429 | $830 | Not Implemented |
MZ0348 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,917 | $1,548 | Implemented |
MZ0348 # 03 Y:2023 | 03 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $5,900 | $2,660 | Not Implemented |
MZ0348 # 02 Y:2023 | 02 | 2023 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $7,209 | $3,330 | Not Implemented |
MZ0348 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $13,016 | $3,000 | Implemented |
OK1088 # 10 Y:2023 | 10 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $20,923 | $16,543 | Not Implemented |
OK1088 # 09 Y:2023 | 09 | 2023 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $6,600 | $14,300 | Not Implemented |
OK1088 # 08 Y:2023 | 08 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,914 | $0 | Not Implemented |
OK1088 # 07 Y:2023 | 07 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,964 | $446 | Not Implemented |