IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

5,708

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0821 # 03 Y:2012 03 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,363 $2,514 Not Implemented
OK0821 # 04 Y:2012 04 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,847 $15,486 Implemented
OK0821 # 05 Y:2012 05 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,712 $15,478 Implemented
OK0821 # 06 Y:2012 06 2012 UPGRADE CONTROLS ON COMPRESSORS $17,137 $0 Implemented
OK0821 # 07 Y:2012 07 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $8,375 $1,700 Implemented
OK0821 # 08 Y:2012 08 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,301 $0 Implemented
OK0821 # 09 Y:2012 09 2012 REPLACE BOILER $21,929 $26,400 Not Implemented
OK0821 # 10 Y:2012 10 2012 INSTALL / REPAIR INSULATION ON STEAM LINES $2,699 $3,135 Not Implemented
OK0821 # 11 Y:2012 11 2012 OPTIMIZE PLANT POWER FACTOR $19,001 $9,750 Not Implemented
OK0819 # 01 Y:2012 01 2012 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $19,728 $10,884 Not Implemented
OK0819 # 02 Y:2012 02 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,891 $16,296 Not Implemented
OK0819 # 03 Y:2012 03 2012 INSTALL OCCUPANCY SENSORS $199 $556 Implemented
OK0819 # 04 Y:2012 04 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,633 $560 Implemented
OK0819 # 05 Y:2012 05 2012 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $15,206 $29,250 Implemented
OK0819 # 06 Y:2012 06 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,466 $0 Not Implemented
OK0819 # 07 Y:2012 07 2012 INSTALL TIMERS AND/OR THERMOSTATS $102 $353 Implemented
OK0819 # 08 Y:2012 08 2012 INSTALL EQUIPMENT TO MOVE PRODUCT $296,539 $350,000 Implemented
OK0818 # 01 Y:2011 01 2011 USE RADIANT HEATER FOR SPOT HEATING $8,413 $91,000 Implemented
OK0818 # 02 Y:2011 02 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,735 $29,626 Not Implemented
OK0818 # 03 Y:2011 03 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,786 $40,503 Not Implemented
OK0818 # 04 Y:2011 04 2011 INSTALL OCCUPANCY SENSORS $309 $2,707 Not Implemented
OK0818 # 05 Y:2011 05 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,726 $1,635 Implemented
OK0818 # 06 Y:2011 06 2011 RECOVER WASTE HEAT FROM EQUIPMENT $1,355 $4,015 Not Implemented
OK0818 # 07 Y:2011 07 2011 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $535 $386 Not Implemented
OK0818 # 08 Y:2011 08 2011 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $482 $2,104 Implemented