Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
146,354
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0042 # 05 Y:1985 | 05 | 1985 | IMPROVE LUBRICATION PRACTICES | $194 | $147 | Not Implemented |
MA0042 # 06 Y:1985 | 06 | 1985 | UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING | $9,886 | $0 | Implemented |
LT0033 # 01 Y:1985 | 01 | 1985 | OPTIMIZE PLANT POWER FACTOR | $10,900 | $12,000 | Implemented |
LT0033 # 02 Y:1985 | 02 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,092 | $400 | Implemented |
LT0033 # 03 Y:1985 | 03 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,004 | $1,862 | Implemented |
LT0033 # 04 Y:1985 | 04 | 1985 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,254 | $510 | Implemented |
LT0033 # 05 Y:1985 | 05 | 1985 | INSULATE BARE EQUIPMENT | $142 | $225 | Implemented |
LT0033 # 06 Y:1985 | 06 | 1985 | INSULATE BARE EQUIPMENT | $302 | $226 | Implemented |
LT0033 # 07 Y:1985 | 07 | 1985 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,592 | $2,250 | Implemented |
LT0033 # 08 Y:1985 | 08 | 1985 | INSTALL TIMERS AND/OR THERMOSTATS | $872 | $300 | Implemented |
LT0033 # 09 Y:1985 | 09 | 1985 | INSULATE BARE EQUIPMENT | $673 | $438 | Implemented |
AT0022 # 01 Y:1985 | 01 | 1985 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $449 | $422 | Implemented |
AT0022 # 02 Y:1985 | 02 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $17,673 | $300 | Implemented |
AT0022 # 03 Y:1985 | 03 | 1985 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $394 | $0 | Implemented |
AT0022 # 04 Y:1985 | 04 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $272 | $250 | Implemented |
AT0022 # 05 Y:1985 | 05 | 1985 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $830 | $450 | Implemented |
AT0022 # 06 Y:1985 | 06 | 1985 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $2,293 | $1,920 | Implemented |
AT0022 # 07 Y:1985 | 07 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,564 | $205 | Implemented |
AT0023 # 01 Y:1985 | 01 | 1985 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $93 | $255 | Not Implemented |
AT0023 # 02 Y:1985 | 02 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $127 | $270 | Not Implemented |
AT0023 # 03 Y:1985 | 03 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,249 | $218 | Not Implemented |
AT0023 # 04 Y:1985 | 04 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $156 | $250 | Implemented |
AT0023 # 05 Y:1985 | 05 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $341 | $125 | Not Implemented |
AT0023 # 06 Y:1985 | 06 | 1985 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $3,785 | $2,700 | Implemented |
AT0024 # 01 Y:1985 | 01 | 1985 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $29 | $70 | Not Implemented |