Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,998
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0060 # 09 Y:1986 | 09 | 1986 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,697 | $1,000 | Implemented |
CO0060 # 10 Y:1986 | 10 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,473 | $17,000 | Implemented |
AT0037 # 01 Y:1986 | 01 | 1986 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,704 | $2,411 | Implemented |
AT0037 # 02 Y:1986 | 02 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $439 | $79 | Implemented |
AT0037 # 03 Y:1986 | 03 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,902 | $300 | Implemented |
AT0037 # 04 Y:1986 | 04 | 1986 | INCREASE AMOUNT OF CONDENSATE RETURNED | $3,940 | $5,000 | Implemented |
AT0037 # 05 Y:1986 | 05 | 1986 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $10,009 | $2,000 | Implemented |
CO0057 # 01 Y:1986 | 01 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $29,471 | $0 | Implemented |
CO0057 # 02 Y:1986 | 02 | 1986 | INSTALL TURBULATORS | $17,475 | $1,800 | Not Implemented |
CO0057 # 03 Y:1986 | 03 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,947 | $2,400 | Not Implemented |
CO0057 # 04 Y:1986 | 04 | 1986 | IMPROVE LUBRICATION PRACTICES | $4,947 | $0 | Not Implemented |
CO0057 # 05 Y:1986 | 05 | 1986 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,412 | $250 | Implemented |
CO0057 # 06 Y:1986 | 06 | 1986 | INSTALL TIMERS AND/OR THERMOSTATS | $739 | $800 | Not Implemented |
CO0057 # 07 Y:1986 | 07 | 1986 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $28,278 | $15,000 | Implemented |
CO0057 # 08 Y:1986 | 08 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,469 | $2,240 | Implemented |
CO0057 # 09 Y:1986 | 09 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,576 | $10,350 | Implemented |
GT0281 # 01 Y:1986 | 01 | 1986 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $735 | $775 | Implemented |
GT0281 # 02 Y:1986 | 02 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $8,681 | $9,090 | Implemented |
GT0281 # 03 Y:1986 | 03 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,835 | $63,595 | Not Implemented |
GT0281 # 04 Y:1986 | 04 | 1986 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $7,813 | $5,158 | Implemented |
GT0281 # 05 Y:1986 | 05 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,561 | $500 | Implemented |
GT0282 # 01 Y:1986 | 01 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $677 | $133 | Implemented |
GT0282 # 02 Y:1986 | 02 | 1986 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $152 | $90 | Implemented |
GT0282 # 03 Y:1986 | 03 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $498 | $300 | Implemented |
GT0282 # 04 Y:1986 | 04 | 1986 | INSTALL / REPAIR INSULATION ON STEAM LINES | $940 | $187 | Implemented |