Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,998
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0056 # 09 Y:1986 | 09 | 1986 | INSTALL TIMERS AND/OR THERMOSTATS | $3,900 | $3,000 | Implemented |
CO0056 # 10 Y:1986 | 10 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,010 | $1,054 | Implemented |
GT0277 # 01 Y:1986 | 01 | 1986 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $443 | $451 | Implemented |
GT0277 # 02 Y:1986 | 02 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,113 | $5,670 | Implemented |
GT0277 # 03 Y:1986 | 03 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $604 | $137 | Implemented |
GT0277 # 04 Y:1986 | 04 | 1986 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $543 | $2,000 | Implemented |
GT0278 # 01 Y:1986 | 01 | 1986 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $15,230 | $7,500 | Implemented |
GT0278 # 02 Y:1986 | 02 | 1986 | HEAT WATER WITH EXHAUST HEAT | $2,590 | $4,000 | Not Implemented |
GT0278 # 03 Y:1986 | 03 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $12,720 | $500 | Implemented |
GT0278 # 04 Y:1986 | 04 | 1986 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,270 | $1,460 | Implemented |
GT0278 # 05 Y:1986 | 05 | 1986 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $203 | $320 | Implemented |
GT0278 # 06 Y:1986 | 06 | 1986 | INSULATE BARE EQUIPMENT | $1,020 | $700 | Not Implemented |
GT0278 # 07 Y:1986 | 07 | 1986 | COVER OPEN TANKS | $156 | $0 | Implemented |
GT0278 # 08 Y:1986 | 08 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,880 | $1,330 | Implemented |
GT0278 # 09 Y:1986 | 09 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,020 | $2,870 | Implemented |
GT0278 # 10 Y:1986 | 10 | 1986 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,270 | $4,900 | Implemented |
GT0279 # 01 Y:1986 | 01 | 1986 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $9,580 | $17,200 | Implemented |
GT0279 # 02 Y:1986 | 02 | 1986 | RECOVER WASTE HEAT FROM EQUIPMENT | $43,200 | $41,600 | Implemented |
GT0279 # 03 Y:1986 | 03 | 1986 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $2,480 | $500 | Implemented |
GT0279 # 04 Y:1986 | 04 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,140 | $500 | Implemented |
GT0279 # 05 Y:1986 | 05 | 1986 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,090 | $1,120 | Implemented |
GT0279 # 06 Y:1986 | 06 | 1986 | COVER OPEN TANKS | $1,560 | $3,000 | Implemented |
GT0279 # 07 Y:1986 | 07 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $670 | $730 | Implemented |
GT0279 # 08 Y:1986 | 08 | 1986 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,157 | $5,063 | Implemented |
GT0279 # 09 Y:1986 | 09 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $950 | $1,650 | Implemented |