IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,380

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0288 # 02 Y:1989 02 1989 REDUCE VENTILATION AIR $30,846 $10,000 Implemented
UD0288 # 03 Y:1989 03 1989 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $23,159 $10,000 Implemented
UD0288 # 04 Y:1989 04 1989 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR $31,629 $90,000 Not Implemented
UD0288 # 05 Y:1989 05 1989 LOWER LIGHT FIXTURES IN HIGH CEILING AREAS $803 $0 Implemented
UD0289 # 01 Y:1989 01 1989 INSTALL TIMERS AND/OR THERMOSTATS $3,618 $1,000 Not Implemented
UD0289 # 02 Y:1989 02 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,453 $0 Implemented
UD0289 # 03 Y:1989 03 1989 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,150 $4,000 Not Implemented
UD0289 # 04 Y:1989 04 1989 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $791 $1,000 Not Implemented
UD0289 # 05 Y:1989 05 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $356 $75 Implemented
UD0289 # 06 Y:1989 06 1989 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $9,331 $25,000 Not Implemented
UD0289 # 07 Y:1989 07 1989 RECOVER AND REUSE COOLING WATER $5,791 $20,000 Not Implemented
WI0054 # 01 Y:1989 01 1989 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $12,498 $35,000 Implemented
WI0054 # 02 Y:1989 02 1989 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER $91,315 $20,000 Implemented
WI0054 # 03 Y:1989 03 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $985 $500 Implemented
WI0054 # 04 Y:1989 04 1989 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $1,279 $6,300 Implemented
WI0054 # 05 Y:1989 05 1989 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $3,752 $4,500 Implemented
WI0054 # 06 Y:1989 06 1989 IMPROVE LUBRICATION PRACTICES $9,728 $0 Not Implemented
WI0054 # 07 Y:1989 07 1989 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $2,931 $0 Implemented
WI0054 # 08 Y:1989 08 1989 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,414 $4,000 Implemented
WI0055 # 01 Y:1989 01 1989 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER $40,435 $0 Implemented
WI0055 # 02 Y:1989 02 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $14,520 $0 Implemented
WI0055 # 03 Y:1989 03 1989 IMPROVE LUBRICATION PRACTICES $8,793 $713 Implemented
WI0055 # 04 Y:1989 04 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,476 $8,464 Implemented
WI0055 # 05 Y:1989 05 1989 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $5,852 $7,000 Implemented
WI0055 # 06 Y:1989 06 1989 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $4,976 $0 Implemented