Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,130
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
ND0166 # 03 Y:1993 | 03 | 1993 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,400 | $1,500 | Implemented |
ND0166 # 04 Y:1993 | 04 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $803 | $459 | Not Implemented |
ND0166 # 05 Y:1993 | 05 | 1993 | INSULATE BARE EQUIPMENT | $651 | $125 | Implemented |
ND0166 # 06 Y:1993 | 06 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $180 | $200 | Not Implemented |
ND0166 # 07 Y:1993 | 07 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $93 | $20 | Implemented |
HO0045 # 01 Y:1993 | 01 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,410 | $2,252 | Implemented |
HO0045 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,086 | $1,095 | Not Implemented |
HO0045 # 03 Y:1993 | 03 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $743 | $1,067 | Not Implemented |
HO0045 # 04 Y:1993 | 04 | 1993 | MOVE BOILER TO MORE EFFICIENT LOCATION | $665 | $1,997 | Not Implemented |
UD0409 # 01 Y:1993 | 01 | 1993 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,772 | $0 | Not Implemented |
UD0409 # 02 Y:1993 | 02 | 1993 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $676 | $2,471 | Implemented |
UD0409 # 03 Y:1993 | 03 | 1993 | INSTALL TIMERS AND/OR THERMOSTATS | $1,251 | $450 | Implemented |
KU0402 # 01 Y:1993 | 01 | 1993 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $29,764 | $80,000 | Not Implemented |
KU0402 # 02 Y:1993 | 02 | 1993 | INSTALL / REPAIR INSULATION ON STEAM LINES | $4,617 | $3,517 | Implemented |
KU0402 # 03 Y:1993 | 03 | 1993 | INSTALL SET-BACK TIMERS | $3,940 | $1,000 | Implemented |
KU0402 # 04 Y:1993 | 04 | 1993 | INSTALL OCCUPANCY SENSORS | $377 | $200 | Not Implemented |
KU0402 # 05 Y:1993 | 05 | 1993 | OPERATE BOILERS ON HIGH FIRE SETTING | $3,802 | $12,100 | Not Implemented |
KU0402 # 06 Y:1993 | 06 | 1993 | USE SYNTHETIC LUBRICANT | $3,674 | $0 | Not Implemented |
KU0402 # 07 Y:1993 | 07 | 1993 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,493 | $11,200 | Not Implemented |
KU0402 # 08 Y:1993 | 08 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,395 | $378 | Not Implemented |
KU0402 # 09 Y:1993 | 09 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,445 | $9,310 | Not Implemented |
KU0402 # 10 Y:1993 | 10 | 1993 | INSTALL TIMERS AND/OR THERMOSTATS | $643 | $440 | Not Implemented |
AS0092 # 01 Y:1993 | 01 | 1993 | USE RADIANT HEATER FOR SPOT HEATING | $917 | $4,000 | Not Implemented |
AS0092 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $216 | $312 | Not Implemented |
AS0092 # 03 Y:1993 | 03 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $102 | $210 | Not Implemented |