Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,230
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0372 # 01 Y:2011 | 01 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,361 | $7,887 | Not Implemented |
MS0372 # 02 Y:2011 | 02 | 2011 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $5,674 | $1,540 | Not Implemented |
MS0372 # 03 Y:2011 | 03 | 2011 | INSTALL TIMERS AND/OR THERMOSTATS | $3,255 | $903 | Not Implemented |
MS0372 # 04 Y:2011 | 04 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,536 | $6,412 | Not Implemented |
MS0372 # 05 Y:2011 | 05 | 2011 | COMBINE UTILITY METERS | $1,264 | $1,300 | Not Implemented |
MS0372 # 06 Y:2011 | 06 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $472 | $528 | Not Implemented |
GT0881 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,620 | $15,500 | Implemented |
GT0881 # 02 Y:2011 | 02 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,731 | $0 | Not Implemented |
GT0881 # 03 Y:2011 | 03 | 2011 | INSTALL COMMON HEADER ON COMPRESSORS | $2,800 | $3,200 | Not Implemented |
GT0881 # 04 Y:2011 | 04 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,921 | $21,722 | Not Implemented |
GT0881 # 05 Y:2011 | 05 | 2011 | DISCONNECT BALLASTS | $588 | $0 | Not Implemented |
GT0881 # 06 Y:2011 | 06 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,188 | $38,276 | Not Implemented |
GT0881 # 07 Y:2011 | 07 | 2011 | REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT | $38,551 | $150,000 | Not Implemented |
GT0881 # 08 Y:2011 | 08 | 2011 | COMBINE UTILITY METERS | $14,342 | $10,000 | Implemented |
WV0427 # 01 Y:2011 | 01 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $34,892 | $74,207 | Not Implemented |
WV0427 # 02 Y:2011 | 02 | 2011 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $9,712 | $42,275 | Not Implemented |
WV0427 # 03 Y:2011 | 03 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $8,998 | $3,390 | Not Implemented |
WV0427 # 04 Y:2011 | 04 | 2011 | ESTABLISH A PREVENTATIVE MAINTENANCE PROGRAM | $6,867 | $637 | Implemented |
WV0427 # 05 Y:2011 | 05 | 2011 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $6,786 | $1,000 | Implemented |
WV0427 # 06 Y:2011 | 06 | 2011 | SHADE WINDOWS FROM SUMMER SUN | $5,176 | $81,597 | Implemented |
WV0427 # 07 Y:2011 | 07 | 2011 | INSTALL OCCUPANCY SENSORS | $4,250 | $1,260 | Not Implemented |
WV0427 # 08 Y:2011 | 08 | 2011 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $4,132 | $2,518 | Not Implemented |
WV0427 # 09 Y:2011 | 09 | 2011 | MODIFY STARTUP/SHUTDOWN TIMES | $3,115 | $975 | Implemented |
WV0427 # 10 Y:2011 | 10 | 2011 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $2,890 | $258 | Implemented |
WV0427 # 11 Y:2011 | 11 | 2011 | DIRECT WASTE GASSES TO BOILER COMBUSTION AIR | $2,312 | $11,063 | Not Implemented |