Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,616
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0348 # 01 Y:2004 | 01 | 2004 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $1,333,121 | $2,700,000 | Implemented |
UF0348 # 02 Y:2004 | 02 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,420 | $29,400 | Implemented |
UF0348 # 03 Y:2004 | 03 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $7,249 | $0 | Implemented |
UF0348 # 04 Y:2004 | 04 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,169 | $10,500 | Implemented |
UF0348 # 05 Y:2004 | 05 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,420 | $22,100 | Not Implemented |
UF0348 # 06 Y:2004 | 06 | 2004 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $39,206 | $74,000 | Implemented |
UF0348 # 07 Y:2004 | 07 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,366 | $0 | Not Implemented |
UF0348 # 08 Y:2004 | 08 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,203 | $6,441 | Implemented |
UF0348 # 09 Y:2004 | 09 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,977 | $456 | Implemented |
UF0348 # 10 Y:2004 | 10 | 2004 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $3,760 | $0 | Implemented |
GT0780 # 01 Y:2004 | 01 | 2004 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $6,020 | $11,903 | Implemented |
GT0780 # 02 Y:2004 | 02 | 2004 | INSTALL TURBULATORS | $11,482 | $12,800 | n/a |
GT0780 # 03 Y:2004 | 03 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,654 | $10,261 | Implemented |
GT0780 # 04 Y:2004 | 04 | 2004 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $25,046 | $92,125 | Not Implemented |
GT0780 # 05 Y:2004 | 05 | 2004 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,772 | $500 | Implemented |
GT0780 # 06 Y:2004 | 06 | 2004 | COMBINE UTILITY METERS | $23,320 | $0 | Not Implemented |
GT0780 # 07 Y:2004 | 07 | 2004 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,729 | $1,209 | Implemented |
GT0780 # 08 Y:2004 | 08 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,512 | $0 | Not Implemented |
GT0780 # 09 Y:2004 | 09 | 2004 | REPAIR AND ELIMINATE STEAM LEAKS | $7,453 | $900 | Implemented |
GT0780 # 10 Y:2004 | 10 | 2004 | CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS | $12,344 | $20,000 | Not Implemented |
GT0780 # 11 Y:2004 | 11 | 2004 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,325 | $1,600 | Not Implemented |
GT0780 # 12 Y:2004 | 12 | 2004 | CONTROL PRESSURE ON STEAMER OPERATIONS | $2,490 | $800 | Implemented |
MS0229 # 01 Y:2003 | 01 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,960 | $16,317 | n/a |
MS0229 # 02 Y:2003 | 02 | 2003 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,125 | $3,106 | Not Implemented |
MS0229 # 03 Y:2003 | 03 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,323 | $7,734 | Not Implemented |