IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

7

matching recommendations
Reset
NAICS 335 Electrical Equipment, Appliance, and Component Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0826 # 01 Y:2012 01 2012 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $17,497 $27,016 Not Implemented
OK0826 # 02 Y:2012 02 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $50,910 $106,879 Not Implemented
OK0826 # 03 Y:2012 03 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $25,061 $38,900 Not Implemented
OK0826 # 04 Y:2012 04 2012 COVER OPEN TANKS $1,576 $0 Not Implemented
OK0826 # 05 Y:2012 05 2012 REDUCE EXCESSIVE BOILER BLOWDOWN $13,280 $31,040 Not Implemented
OK0826 # 06 Y:2012 06 2012 INSTALL / REPAIR INSULATION ON STEAM LINES $4,630 $4,000 Not Implemented
OK0826 # 07 Y:2012 07 2012 INSTALL / REPAIR INSULATION ON STEAM LINES $20,532 $9,400 Not Implemented