Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
101
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0433 # 03 Y:2006 | 03 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,142 | $7,500 | n/a |
AS0433 # 01 Y:2006 | 01 | 2006 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $34,471 | $30,000 | n/a |
AS0433 # 04 Y:2006 | 04 | 2006 | INSTALL EFFICIENT RECTIFIERS | $540 | $15,000 | n/a |
AS0433 # 02 Y:2006 | 02 | 2006 | USE SOLAR HEAT TO HEAT WATER | $13,683 | $78,400 | n/a |
AS0432 # 04 Y:2006 | 04 | 2006 | INSTALL EFFICIENT RECTIFIERS | $540 | $15,000 | n/a |
AS0432 # 01 Y:2006 | 01 | 2006 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $17,236 | $15,000 | n/a |
AS0432 # 03 Y:2006 | 03 | 2006 | SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING | $9,888 | $3,000 | n/a |
AS0432 # 02 Y:2006 | 02 | 2006 | USE SOLAR HEAT TO HEAT WATER | $13,683 | $78,400 | n/a |
AS0431 # 02 Y:2006 | 02 | 2006 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,413 | $1,500 | n/a |
AS0431 # 01 Y:2006 | 01 | 2006 | USE SOLAR HEAT TO HEAT WATER | $1,728 | $8,800 | n/a |
AS0431 # 03 Y:2006 | 03 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $529 | $1,500 | n/a |
AS0431 # 05 Y:2006 | 05 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $370 | $1,000 | n/a |
AS0431 # 04 Y:2006 | 04 | 2006 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $401 | $1,500 | n/a |
AS0430 # 04 Y:2006 | 04 | 2006 | INSTALL SKYLIGHTS | $782 | $4,400 | Implemented |
AS0430 # 01 Y:2006 | 01 | 2006 | USE SOLAR HEAT TO MAKE ELECTRICTY | $136,800 | $2 | Not Implemented |
AS0430 # 03 Y:2006 | 03 | 2006 | INSULATE BARE EQUIPMENT | $3 | $1,077 | Implemented |
AS0430 # 02 Y:2006 | 02 | 2006 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $9,545 | $7,500 | Implemented |
AS0430 # 05 Y:2006 | 05 | 2006 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $770 | $1,000 | Not Implemented |
AS0428 # 01 Y:2006 | 01 | 2006 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $15,000 | $0 | n/a |
AS0429 # 02 Y:2006 | 02 | 2006 | INSULATE BARE EQUIPMENT | $2,039 | $500 | n/a |
AS0428 # 06 Y:2006 | 06 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,348 | $5,000 | n/a |
AS0428 # 03 Y:2006 | 03 | 2006 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,918 | $2,500 | n/a |
AS0428 # 05 Y:2006 | 05 | 2006 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,252 | $1,500 | n/a |
AS0428 # 04 Y:2006 | 04 | 2006 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,269 | $5,600 | n/a |
AS0429 # 01 Y:2006 | 01 | 2006 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,688 | $1,000 | n/a |