Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
500
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CI0027 # 06 Y:2023 | 06 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,620 | $0 | n/a |
CI0027 # 07 Y:2023 | 07 | 2023 | USE PHOTOCELL CONTROLS | $3,161 | $1,400 | n/a |
CI0027 # 03 Y:2023 | 03 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $16,307 | $15,500 | n/a |
CI0027 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $24,353 | $300 | n/a |
CI0027 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $64,706 | $1,076,000 | n/a |
CI0027 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,618 | $2,442 | n/a |
CI0027 # 08 Y:2023 | 08 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,655 | $500 | n/a |
CI0027 # 05 Y:2023 | 05 | 2023 | INSTALL OCCUPANCY SENSORS | $3,632 | $3,000 | n/a |
CI0026 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $6,141 | $80,118 | n/a |
CI0026 # 06 Y:2023 | 06 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,873 | $8,074 | n/a |
CI0026 # 08 Y:2023 | 08 | 2023 | SEPARATE CONTROLS OF AIR HANDLERS FROM AC/ HEATING SYSTEMS | $458 | $400 | n/a |
CI0026 # 01 Y:2023 | 01 | 2023 | REPLACE BOILER | $40,642 | $20,000 | n/a |
CI0026 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,454 | $2,400 | n/a |
CI0026 # 02 Y:2023 | 02 | 2023 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $21,942 | $60,000 | n/a |
CI0026 # 04 Y:2023 | 04 | 2023 | USE PHOTOCELL CONTROLS | $3,866 | $2,700 | n/a |
CI0026 # 07 Y:2023 | 07 | 2023 | INSTALL OCCUPANCY SENSORS | $500 | $2,000 | n/a |
CI0025 # 01 Y:2023 | 01 | 2023 | USE BATTERY STORAGE FOR DEMAND CONTROL | $81,464 | $500,000 | n/a |
CI0025 # 07 Y:2023 | 07 | 2023 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,793 | $100 | n/a |
CI0025 # 02 Y:2023 | 02 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $63,063 | $212,582 | n/a |
CI0025 # 03 Y:2023 | 03 | 2023 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $8,140 | $17,500 | n/a |
CI0025 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,867 | $7,205 | n/a |
CI0025 # 05 Y:2023 | 05 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,405 | $0 | n/a |
CI0025 # 06 Y:2023 | 06 | 2023 | USE PHOTOCELL CONTROLS | $2,875 | $2,520 | n/a |
CI0024 # 05 Y:2023 | 05 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,729 | $0 | n/a |
CI0024 # 07 Y:2023 | 07 | 2023 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $1,423 | $15,000 | n/a |