IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

184

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CO0058 # 03 Y:1986 03 1986 INSTALL TIMERS AND/OR THERMOSTATS $2,654 $1,100 Implemented
CO0058 # 04 Y:1986 04 1986 BURN WOOD BY-PRODUCTS FOR HEAT $27,671 $32,700 Implemented
CO0058 # 05 Y:1986 05 1986 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,134 $400 Implemented
CO0058 # 06 Y:1986 06 1986 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $176 $500 Implemented
CO0058 # 08 Y:1986 08 1986 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $340 $100 Implemented
CO0058 # 09 Y:1986 09 1986 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $405 $100 Implemented
CO0058 # 10 Y:1986 10 1986 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,182 $1,183 Implemented
CO0059 # 01 Y:1986 01 1986 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $34,952 $300 Implemented
CO0059 # 04 Y:1986 04 1986 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $667 $150 Implemented
CO0059 # 07 Y:1986 07 1986 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $314 $50 Implemented
CO0059 # 08 Y:1986 08 1986 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS $2,338 $160 Implemented
CO0059 # 10 Y:1986 10 1986 INSTALL TIMERS AND/OR THERMOSTATS $5,248 $55 Implemented
CO0059 # 11 Y:1986 11 1986 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $740 $655 Implemented
CO0060 # 03 Y:1986 03 1986 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,357 $300 Implemented
CO0060 # 05 Y:1986 05 1986 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $433 $25 Implemented
CO0060 # 07 Y:1986 07 1986 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $734 $930 Implemented
CO0060 # 09 Y:1986 09 1986 RECOVER WASTE HEAT FROM EQUIPMENT $1,697 $1,000 Implemented
CO0060 # 10 Y:1986 10 1986 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,473 $17,000 Implemented
CO0057 # 01 Y:1986 01 1986 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $29,471 $0 Implemented
CO0057 # 05 Y:1986 05 1986 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,412 $250 Implemented
CO0057 # 07 Y:1986 07 1986 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER $28,278 $15,000 Implemented
CO0057 # 08 Y:1986 08 1986 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,469 $2,240 Implemented
CO0057 # 09 Y:1986 09 1986 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $11,576 $10,350 Implemented
CO0056 # 01 Y:1986 01 1986 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,978 $200 Implemented
CO0056 # 02 Y:1986 02 1986 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $252 $200 Implemented