Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

63

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
DL0010 # 07 Y:2007 07 2007 INSTALL OCCUPANCY SENSORS $454 $524 Not Implemented
DL0010 # 06 Y:2007 06 2007 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $622 $622 Not Implemented
DL0010 # 05 Y:2007 05 2007 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,409 $0 Implemented
DL0010 # 04 Y:2007 04 2007 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,529 $450 Implemented
DL0010 # 03 Y:2007 03 2007 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR $4,305 $225 Implemented
DL0010 # 02 Y:2007 02 2007 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) $9,440 $2,500 Not Implemented
DL0010 # 01 Y:2007 01 2007 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $10,964 $2,872 Implemented
DL0009 # 05 Y:2007 05 2007 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $11,192 $50,000 Implemented
DL0009 # 11 Y:2007 11 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,550 $20,000 Implemented
DL0009 # 08 Y:2007 08 2007 RECOVER WASTE HEAT FROM EQUIPMENT $1,941 $590 Not Implemented
DL0009 # 10 Y:2007 10 2007 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $4,500 $4,968 Not Implemented
DL0009 # 12 Y:2007 12 2007 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $310 $160 Not Implemented
DL0009 # 13 Y:2007 13 2007 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $302 $10,000 Implemented
DL0009 # 14 Y:2007 14 2007 USE SOLAR HEAT TO MAKE ELECTRICTY $20,475 $1,275,000 Not Implemented
DL0009 # 09 Y:2007 09 2007 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $4,924 $3,809 Implemented
DL0009 # 07 Y:2007 07 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,890 $695 Implemented
DL0009 # 06 Y:2007 06 2007 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,454 $0 Not Implemented
DL0009 # 04 Y:2007 04 2007 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $10,793 $11,313 Not Implemented
DL0009 # 03 Y:2007 03 2007 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) $11,200 $60,000 Not Implemented
DL0009 # 02 Y:2007 02 2007 REDESIGN PROCESS $15,567 $6,300 Not Implemented
DL0009 # 01 Y:2007 01 2007 INSTALL / REPAIR INSULATION ON STEAM LINES $28,059 $10,000 Implemented
DL0008 # 05 Y:2007 05 2007 USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE $18,000 $1,000 Implemented
DL0008 # 04 Y:2007 04 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $20,801 $175,000 Implemented
DL0008 # 03 Y:2007 03 2007 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $31,900 $0 Implemented
DL0008 # 02 Y:2007 02 2007 REPLACE BOILER $33,159 $102,000 Not Implemented